GIF++ installation and schedule meeting

Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

Attendance:
————

Giuseppe (DT-DD)

Mara C. (DT)

Katerina K. (CMS-CSC)

Sergio (CMS-DT)

Matteo (CMS-RPC)

Vidyo:
----------

Lisa B. (CMS-GEM)

Daniele Fasanella (CMS-DT)

 

There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of beam weeks operation 10m
    • 09:20 09:30
      Plans for upcoming week 10m

      Wednesday 25th:

      - Beam pipe removed

      - Intervention on the access control matrix system

      Thursday  October 26th: 

      Source Scan 5h from 10h30 downstream for CMS-CSC, CMS-DT, DT-FS.

      Upstream  - no source scan filter scan combination will stay 112 

       

      No request to open bunker on Wednesday 01 November

      From Monday low irradiation - downstream to start on 30.10.  (start with 40, then going to 22)

       

    • 09:30 09:45
      Muon Beam Time GIF - Final Days 15m
      • Report from Downstream Field 5m
      • Report from Upstream Field 5m
    • 09:45 09:55
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ALICE electronic board to return for 1-2 weeks. we will try to host it in the upstream area this time, possible hosted by the ATL-MM

       

      RADMON system to be re-installed next week

       

       

       

    • 09:55 10:10
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      • Upgrade of GIF Control System - Initial list submitted to DT controls group
      • Two Berthold probes to be available after October

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Requirements during YETS and LS2 5m

        Rack cooling will not be available for the YETS.
        CMS-CSC to check if  local chiller is available, otherwise help from EN-CV is needed.

      • Upcoming Interventions 5m

        Material Door, cooling perturbations,

        To be scheduled :
        ----------------------

        Bunker door ready to be installed  - new door (3.2m high) agreed - installation 6-9. Nov.

        YETS : water cooling stop for basically the full end of the year stop.

      • New Extraction Line - Gas System 5m

        Requirements for the new extraction line

    • 10:10 10:20
      Announcements 10m
      • New Announcements 5m
      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours.

      • AOB 5m

        Gas  bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
        Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.

        Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
        To be clarified with Roberto & Fred.

        O2 contamination study - Roberto to comment.