GIF++ installation and schedule meeting

Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

Attendance:
————

Giuseppe (DT-DD)

Mara C. (DT)

Katerina K. (CMS-CSC)

Sergio (CMS-DT)

Matteo (CMS-RPC)

Vidyo:
----------

Lisa B. (CMS-GEM)

Daniele Fasanella (CMS-DT)

 

There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation 10m
    • 09:25 09:35
      Plans for upcoming week 10m

      IRRADIATOR STOP POSTPONED - No new time known.

      Next week : If MADS installation further postponed - opening of bunker on Wednesday.
      Cable installation for CMS-DT.

       

      Today 9. Nov. :
      --------------------

      Downstream :  CMS-DT : Filter scan 3h  with short access art beginning and end (10min).
      Upstream :  No announcement

       

       

    • 09:35 09:50
      Planning for the comming weeks 15m
      • Report from Downstream Field 5m
      • Report from Upstream Field 5m
    • 09:50 10:00
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ALICE electronic board to return for 1-2 weeks. we will try to host it in the upstream area this time, possible hosted by the ATL-MM

       

      RADMON system to be re-installed next week

       

       

       

    • 10:00 10:15
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      • Upgrade of GIF Control System - Initial list submitted to DT controls group
      • Two Berthold probes to be available after October

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Material Door Installation 5m
      • Upcoming Interventions 5m
      • Requirements during YETS and LS2 5m

        YETS : water cooling stop for basically the full end of the year stop.CMS-CSC to check if  local chiller is available, otherwise help from EN-CV is needed.

    • 10:15 10:25
      Announcements 10m
      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). If your work is outside, please state the whole number of hours.

      • New Announcements 5m
      • AOB 5m

        Gas  bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
        Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.

        Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
        To be clarified with Roberto & Fred.

        O2 contamination study - Roberto to comment.