GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of last week operation & plans for this week 10m
-
09:25
→
09:40
Planning for the comming weeks 15m
-
Report from Downstream Field 5m
-
Report from Upstream Field 5m
-
- 09:40 → 09:50
-
09:50
→
10:05
Infrastructure & Upgrades to the Facility 15m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Ongoing Projects :
Retrieval of TIMBER values : Work in progress, but already available in beta version
Test site : http://epdtdi-vm-01.cern.ch:8080/pytimberAdditional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only
-
Upcoming Interventions 5m
ANNUAL AUG TEST will be the Tue. 9. Jan.
Access System not operational : 09-11 January 2018 -> SOURCE OFF
-> We therefore restart normal operation after Christmas break on FRIDAY 12.01 (!)Local AUG test : 5-7 March. Will be announced in more details when closer to the test.
Annual Irradiator Maintenance : March 12-14 2018
DSO Test : March 15 2018Field mapping campaign (?) proposed before/after Maintenance. ≈ 3 Days.
-
10:05
→
10:15
Announcements 10m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
Muon Beam Time 2018 5m
Update on the SPS Planning
-
IMPACTS for 2018 5m
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)
Special IMPACT needed for Christmas Closure.
-
AOB 5m
Gas bill 2016 : please note that the EP-DT budget for GIF does not cover consumables.
Gas used at the GIF++ will have to be paid by the consumer. We will start the TID's soon.Question from Barbara : How is the Argon/CO2 provided, and will this be charged to the user.
To be clarified with Roberto & Fred.O2 contamination study - Roberto to comment.
-
-