GIF++ installation and schedule meeting

Europe/Zurich
892/1-D20 (CERN)

892/1-D20

CERN

45
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

Attendance:
————

Vidyo:

 

----------

There are minutes attached to this event. Show them.
    • 09:15 09:25
      Review of last week operation & plans for this week 10m

      EP-DT : Moved out.

      1h- source OFF after the meeting.  (access)
      Access 14h for - 30 minutes
      Access in the evening for 10 minutes


      Downstream : 

      CMS-CSC source scan 6.9 stable for several hours.
      CMS-DT : Friday 2h filterscan
      Possible scan for GEM on Friday (to be confirmed)


      Upstream :

      CMS-RPC  2.2-6.9 filter scan
      Friday 2h with filter 333 on request of CMS-DT

       

    • 09:25 09:40
      Planning for the comming weeks & Muon Beam Weeks 15m

      Wednesday ATL-RPC and CMS-RPC , stop of gas System for 2h
      Install cable tray upstream. - to be discussed.

      FOR NEXT WEEK MAINTENANCE, please look at the INFRASTRUCTURE section below.

      • Report from Downstream Field 5m
      • Report from Upstream Field 5m
    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

       

       

    • 09:50 10:05
      Infrastructure & Upgrades to the Facility 15m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Ongoing Projects :

      Retrieval of TIMBER values : Work in progress, but already available in beta version
      Test site : http://epdtdi-vm-01.cern.ch:8080/pytimber

      Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only
       

       

      • Upcoming Interventions - ANNUAL MAINTENANCE 5m

        Planned AUG test for EHN1 : 6.03  - Finished around Lunch time.
        Unexpected cut of EHN1 on 7.03. AUG tests still ongoing in north area.

        Some problems of restarting Irradiator after cut.
        So be understood.

        Schedule of the Maintenance period :

        Monday 12.03 : Removal of detector setups from bunker area, preparation of bunker.
        Tuesday 13.03 : Opening of the roof Upstream
                                  Installation of Scaffolding
        Annual Irradiator Maintenance : 13-15 03 2018
        In Parallel : Maintenance of the Access System, PR - maintenance of REMUS, Gas Detection Maintenance.
        Installation of cable tray for Cosmic Trigger Roof Chamber
        Installation of a shielded electronic rack
        Friday 16.03 :
        DSO Test 14h
        Saturday - Sunday : 17-18.03 Field Mapping with Dose Meter
        Monday 18.03 : Field Mapping with Spectrometer
        Tuesday 20.03 : Re-installations of setups into bunker.
                                  Access day (instead of Monday)
                                   Source ON possible in the evening
        Wednesday 21.03 : Restart of normal operation

         

      • Requirements during LS2 5m
    • 10:05 10:15
      Announcements 10m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • Muon Beam Time 2018 5m

        Update on the SPS Planning

      • IMPACTS for 2018 5m

        Guidelines for filling in IMPACT requests

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)

        Special IMPACT needed for Christmas Closure.

      • New Announcements 5m
      • AOB 5m