Participants: Simon Albright, Fanouria Antoniou, Jean-Baptiste Bonnamy, Jean-François Comblin, Gian Piero Di Giovanni, Tobias Dobers, Alessandro Floriduz, Vincenzo Forte, Anne Funken, Eve Fortescue-Beck, Jean-Louis Grenard, Matthias Haase, Alessandra Lombardi, Bettina Mikulec, Antony Newborough, Gabor Petrika, Fabio Pozzi, Andrea Santamaria Garcia, Frank Schmidt, Jocelyn Tan, Wim Weterings.

Approval of minutes

The minutes of the LIU-PSB WG #218 and LIU-PSB WG #219 meeting were approved.

Communications

LIU-PT Meeting

Open actions

M. Buzio (2018-08-28): Investigate and report the options for implementing an online field measurement in the switching dipole BT.BHZ10.

I. Lamas (2018-06-19): Prepare the ECR for the PSB scraper/absorber describing both the dismantling of the current equipment and the installation of the new one.

I. Efthymiopoulos (2018-06-19): Make a list of starting points of the transfer lines to be sent for approval in an EDMS document.

T. Dobers (2018-06-19): Produce the tilt measurement tool and perform measurements on spare / future magnets.

Marking of LIU cables by equipment owners on both ends before the start of LS2 and disconnection of cables immediately after the end of the 2018 run.

Status of the LIU-PSB Safety File and next steps (A. Funken)

The Safety Package (SP) concept was introduced to the safety file due to the extent of the project, which covers the upgrade of five accelerators. The LIU project has 15 SPs and 90 Work Packages (WPs). A Safety Package Coordinator (SPC) is appointed for each SP, acting as the technical link person for the corresponding SP.

The LIU-PSB Safety File (link to EDMS)

The LIU-PSB has four SPs and their associated SPCs:

Each SP has:

Additionally, there are two demonstrative parts associated to the PSB machine (PSB Rings, Injection and Extraction) and to building 245 being updated before submission to the PL. In the demonstrative part the hazards have been identified and the foreseen control measures listed, as well as a qualitative risk assessment for each equipment/system.

Safety Compliance of Equipment

Safety compliance of the LIU equipment has to be demonstrated by asking HSE for safety inspections and pre-visits by HSE experts for electrical equipment.

A. Funken prepared Excel files to collect the needs for HSE pre-visit and inspections: https://edms.cern.ch/document/1212097/1

G. P. Di Giovanni circulated the files beginning of July for the electrical pre-visit and inspections. The Linac4 connection shall also be included, as well as the forecast for pressure inspections.  

Action: All the WP-holders are requested to provide the needed information to A. Funken by filling the forms attached in this Indico event as soon as possible (electrical and pressure inspections).

It is proposed that A. Funken coordinates this action after receiving the list of the LIU-PSB equipment responsibles. She will then organize dedicated meetings with HSE and the equipment groups to clarify and agree on the list of safety documents to be provided, in particular for the inspections

Comments

EN-CV activities and status (G. Petrika)

There are four Work Packages (WP) concerning the LIU-PSB:

Cooling

Scope

Status and next steps

Chilled Water

Scope

The chilled water plant is currently in building 361 (in the PSB building) and it will be moved to building 141.

Status and next steps

POPS cooling modification

Cancelled activities

Miscellaneous

Comments

PSB and Linac4 Applications Development during LS2 (J-F. Comblin)

J.F. Comblin presented the list of applications being developed by the BE-OP-PSB group for the operation of the Linac4 and the PSB. Below a summary table:

Application

Delivery Date

Responsible

Estimated Time

LN4 Longitudinal Emittance

June 2019

Y. Wu

2 Months

LN4 Transverse Emittance.

June 2019

T. Bukovics / J-F Comblin

3 Months

Time of Flight

June 2019

A. Akroh

1 Month

Energy Meas. with Beam Loading

June 2019

A. Akroh

1 Month

Cruise Control

End of LS2

A. Akroh

2 Months

Laser Emittance Measurement

End of LS2

V. Barbet

1.5 Months

S.I.S.

June 2019 for LN4, End of LS2 for PSB

T. Bukovics / M. Gabriel

2 Months

Wire Scanner Application

End of LS2

J-F Comblin

1.5 Month

BLMs

End of LS2

Y. Wu

2.5 Months

Matching Monitor

End of LS2

J-F Comblin

0.5 Month

H0/H- Monitor

End of LS2

T. Bukovics

1 Month

Extraction Kickers Control

End of LS2

A. Akroh

0.5 Month

POPS-B Control

End of LS2

V. Barbet / J-F Comblin / JM Nonglaton

2 Months

Tune Control

End of LS2

V. Barbet / J-F Comblin / JM Nonglaton

3 Months

YASP Configuration

End of LS2

J-F Comblin

0.5 Month

Review and Update of Logging

End of LS2

Y. Wu

1 Month

Misc. (Update of app., knobs, W-Sets)

End of LS2

Y. Wu / A. Akroh / J-F Comblin / V. Barbet

4 x 1 Month

Total

 

5 programmers

(3 experimented + 2 novices)

~ 2.5 FTE

 

List of actions:

Comments

Tour de table

Next LIU-PSB meeting: 11th of September 2018 TE-MSC activities and status by A. Newborough and an EVM report update by S. Prodon.