LIU - Planning & Installation meeting

→ Europe/Zurich
376/1-020 (CERN)

376/1-020

CERN

16
Show room on map
    • 16:00 → 16:05
      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-SPS ECR SPS-VC-EC-0004 (EDMS1946438) Modification of 25 QD Short Straight Sections configurations in SPS 15m

      Horizontal aperture scans detected a systematic asymmetry in the aperture at the level of the QD short straight sections all around the SPS machine. The origin of the aperture restriction was traced back to the eccentric bellow at the MBB to SSS(QD) transition. These limitations explain partially the reduced lifetime with high intensity 25 ns proton beam and Q20 optics at the injection flat bottom. During YETS17/18 three vacuum drifts OD159/ID156 have been installed temporarily in positions 10110,11310 and 40110 as described in [3].
      The aperture restriction will be solved by changing the configuration of the interconnection with a asymetric aperture flange and a straight bellow, and a modification of the pumping port shielding. Out of 108 QD SSS around the ring, 25 locations will be tackled during LS2.

      Speakers: Chiara Pasquino (CERN), Verena Kain (CERN)
    • 16:25 → 16:40
      LIU-SPS ECR SPS-BWSRC-EC-0001 (EDMS1969742) New Rotatable Beam Wire Scanner Installation in the SPS Ring 15m

      It is proposed to replace 4 existing wire scanners in half-periods 41610-41710 and 51910-52010 by 4 rotatable beam wire scanners of new generation. The devices are used to measure and reconstruct the beam profile. The installation will take place during the LS2 as part of the LIU project.

      Speakers: Dmitry Gudkov (ESS - European Spallation Source (SE)), Raymond Veness (CERN), William Andreazza (CERN)
    • 16:40 → 16:50
      AoB 10m