LIU - Planning & Installation meeting

→ Europe/Zurich
376/1-020 (CERN)

376/1-020

CERN

16
Show room on map
    • 16:00 → 16:05
      Approval of the minutes 5m
      Speaker: Julie Coupard (CERN)
    • 16:05 → 16:10
      LIU-PLI Follow-up 5m
      • Follow-up on the SRRs and ECRs
      Speaker: Julie Coupard (CERN)
    • 16:10 → 16:25
      LIU-SPS ECR SPS-VC-EC-0005 (EDMS1968345) SPS amorphous carbon coating in LS2 2019-2020 15m

      An amorphous carbon (aC) coating of the SPS MBB dipoles, QD and QF quadrupoles, short straight sections and long straight sections is proposed in order to supress electron cloud effects in the machine.

      During LS2: Amorphous Carbon coating of the chambers of all QF that didn't have an aC coating yet, including adjacent QF SSS; all remaining 159 mm diameter drift tubes in all LSS; the chambers of remaining MBBs in 5- ,5+ and 6- (up to 603 included), including adjacent QD quadrupoles and QD SSS multipoles.

      ECR: 1852436 (YETS 2017-2018)
      ECR: 1719610 (EYETS 2016-2017)

      Speaker: Wilhelmus Vollenberg (CERN)
    • 16:25 → 16:40
      LIU-SPS ECR SPS-VF-EC-0004 (EDMS1968756) SPS Flange Impedance Reduction in LS2 15m

      The shielding of the known cavities in the vacuum system interconnections of the Short Straight Sections adjacent to the QF quadrupoles is proposed to improve the longitudinal impedance of the machine.

      Installation of shielding solutions in 173 vacuum flange junctions. The previous campaigns were described in SPS-VF-EC-0001 and SPS-VF-EC-0003.

      Speaker: Jaime Perez Espinos (CERN)
    • 16:40 → 17:00
      LIU-PSB ECR PSB-MK-EC-0001 (EDMS1955039) New PS Booster Recombination Kicker Magnet BT.KFA10 20m

      After LS2 the PSB will operate at an extraction energy of 2GeV and for this reason the transfer kicker BT.KFA10 has to be upgraded. In order to achieve this new magnets are constructed, based on the existing design, but with improved performance by changing the type of ferrite previously used.

      Speaker: Wim Weterings (CERN)
    • 17:00 → 17:20
      LIU-SPS ECR SPS-R-EC-0003 (EDMS1874303) Power converter modifications in building BA1 required by LIU-SPS 20m

      In order to comply with the framework of SPS Beam dump relocation, the actual BA1 converters layout shall be modified as described in this document.
      Plan number: 11103.

      Speaker: Emilien Coulot (CERN)
    • 17:20 → 17:30
      AoB 10m