Present: J. Caeyman, P. Collet, M. De Saegher, J. Lehrbach, L. Roy, H. Schindler, R. Schwemmer, B. Vindevogel
Module construction status
- Racks and load banks of the first ALICE IT modules are being installed (see the picture uploaded to the agenda page).
- Lubron is coming to Automation this week to start up the RO plant.
- 1 MW generator is being installed.
- Work on LHCb power module starting soon.
Drawings
- STEP files for LHCb remaining LHCb IT modules have been uploaded.
- Michel has uploaded drawings for the hinges and pictures of the unloading.
RO installation
- Patrick has sent an updated Life Cycle Cost estimation from Stulz.
- The RO plant includes a buffer tank which should be able to bridge up to 9h at extreme temperatures, when the required water consumption exceeds the production capacity of the plant. As a backup option, the installation also includes a bypass valve to use softened water instead of RO water.
FATs
- ALICE FAT has been delayed. ALICE to check the dates proposed by Automation.
- Johannes explained that he can't discuss the FAT protocol, this has to be discussed with ALICE project management first.
- Johannes clarified that he can't make any statement about the contract, this has to be discussed with the CERN procurement service.
- ALICE will try to discuss the requests about the FAT protocol this week, no promise/commitment though.
- LHCb FAT scheduled for 11/12 September.
Action items
- Automation to upload/send through structural calculations for LHCb.
- ALICE/LHCb to review the uploaded LCC/water consumption calculations.
- Automation to ask Lubron for an estimate of the expected RO water temperature given a raw water temperature range of 10 - 15° C.
- Automation to take pictures of the possible locations for the fire detection "box".
- ALICE/LHCb to check with the CERN access control group where to route the cables from the door contacts.
- ALICE/LHCb to collate questions/comments regarding the documentation of the MODBUS registers.
- CERN to send four water manifold boxes to Automation (2 ALICE + 2 LHCb) and inform Automation as soon as the shipment date is known.
- LHCb to send information which racks should have a cut-out in the side panels and their layout.
Next meeting: Tuesday 10 July at 13.30.