Schedule for Post LS2 commissioning with inputs from PS and SPS:
- HW commissioning: 5 weeks of individual system tests
- PSB will start on the 2nd week of September 2020 ==> 2.5 months of beam commissioning
- First beams:
- SFTPRO (RF setup can be done with H1 using H2 timing)
- SPS needs LHCINDIV (4 rings) from the beginning to setup the RF. Minimum measurable pulse length for Linac4 diagnostics = 150 ns (is longitudinally shaving needed?), To be confirmed that this length is fine also for PSB diagnostics (matching monitor, BLMs, turn-by-tunr BPMs etc., to be confirmed by Federico)
- TOF: RF can work on ring 3 (keeping parasitic ring 2). It has to be checked with PS if this option is fine for nominal operation.
- Experiments: need to define dates (MTE beam main challenge!)
- Longitudinal painting:
- Optimum to be defined by RF (Simon) and used as an input for ABT and ABP simulations on injection and space charge. Possible iterations in case of issues.
- This year we should aim for testing the basic functionalities (provide RF with specs for momentum spread, swing and chopping pattern for next meeting, Simon with inputs from Vincenzo’s past simulations for ISOLDE)
- Next year: test ppm functionality assuming different intensities for the different rings, etc. ==> organise a meeting with RF after converging to 1! request from our side.
- Need to define simulations and priorities for different commissioning scenarios with and without long. painting etc. (Chiara, Vincenzo and Fanouria)