Conveners
Session 2: LS2 system readiness and shutdown execution
- Julie Coupard (CERN)
- Brennan Goddard (CERN)
Session 2: LS2 system readiness and shutdown execution
- Brennan Goddard (CERN)
- Julie Coupard (CERN)
Session 2: LS2 system readiness and shutdown execution
- Brennan Goddard (CERN)
- Julie Coupard (CERN)
-
Giovanni Rumolo (CERN)14/02/2019, 10:30
- Overview of spares for start-up – identifying whether the available spares can be considered ready to use or they need testing/other procedure(s) before being used
- List known NCs or variation from specified equipment performance, and impact (to be discussed here should be impact on schedule, while impact on performance should be addressed in collaboration with S1)
- Catalogue of upgrades...
-
Jose Miguel Jimenez (CERN)14/02/2019, 11:00
- Overview on the organisation of the LS2 (organigram, reporting lines, responsibilities)
- Committee structure, mandate and frequency (LS2C, machine shutdown coordination, …)
- Mechanisms for handing delays, problems and unforeseen eventualities
-
Simon Mataguez (CERN)14/02/2019, 11:20
- Planning overview and breakdown
- Major activities and critical path analysis
- Highlight on LIU activities
- Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
- Co-activities
- Milestones of general services availability
- Remaining issues/uncertainties
-
David Hay (CERN)14/02/2019, 11:40
◾Planning overview and breakdown
Go to contribution page
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties -
Fernando Baltasar Dos Santos Pedrosa (CERN)14/02/2019, 12:00
◾Planning overview and breakdown
Go to contribution page
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties -
David Mcfarlane (CERN)14/02/2019, 12:20
◾Planning overview and breakdown
Go to contribution page
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties -
Anne Funken (CERN)14/02/2019, 14:00
- LIU Safety objectives
- LIU Safety documentation (organisation, LIU safety packages, methodology for the descriptive and demonstrative parts of the LIU safety files)
- Conformity of the LIU equipment to the CERN Safety rules and the regulation, and process of HSE electrical pre-visits
- Safety milestones towards beam permits
-
Julie Coupard (CERN)14/02/2019, 14:30
- Activities by group across all facilities
- Known resource conflicts
-
Jonathan Pascal Meignan (CERN)14/02/2019, 14:50
- Readiness for Installation dates per group with present equipment status (STI, EPC, ABT, BI, RF, MSC, VSC)
- Risk analysis of LIU equipment:
Identify critical delivery path items (or already late) - Evaluate the impact on the shutdown activities
- Discuss mitigation (with agreed methodology)
-
Valerie Montabonnet (CERN)14/02/2019, 15:10
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
-
Frank Gerigk (CERN)14/02/2019, 16:10
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
-
Etienne Carlier (CERN)14/02/2019, 16:40
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
-
Francois-Xavier Nuiry (CERN)14/02/2019, 17:10
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
-
Brennan Goddard (CERN), Julie Coupard (CERN)14/02/2019, 17:40