Conveners
Session 2: LS2 system readiness and shutdown execution
- Julie Coupard (CERN)
- Brennan Goddard (CERN)
Session 2: LS2 system readiness and shutdown execution
- Brennan Goddard (CERN)
- Julie Coupard (CERN)
Session 2: LS2 system readiness and shutdown execution
- Brennan Goddard (CERN)
- Julie Coupard (CERN)
- Overview on the organisation of the LS2 (organigram, reporting lines, responsibilities)
- Committee structure, mandate and frequency (LS2C, machine shutdown coordination, …)
- Mechanisms for handing delays, problems and unforeseen eventualities
- Planning overview and breakdown
- Major activities and critical path analysis
- Highlight on LIU activities
- Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
- Co-activities
- Milestones of general services availability
- Remaining issues/uncertainties
◾Planning overview and breakdown
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties
◾Planning overview and breakdown
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties
◾Planning overview and breakdown
◾Major activities and critical path analysis
◾Highlight on LIU activities
◾Dependencies and impact between LIU and other ongoing projects in LS2 (e.g. CONS, Fire Safety, HL-LHC)
◾Co-activities
◾Milestones of general services availability
◾Remaining issues/uncertainties
- LIU Safety objectives
- LIU Safety documentation (organisation, LIU safety packages, methodology for the descriptive and demonstrative parts of the LIU safety files)
- Conformity of the LIU equipment to the CERN Safety rules and the regulation, and process of HSE electrical pre-visits
- Safety milestones towards beam permits
- Activities by group across all facilities
- Known resource conflicts
- Readiness for Installation dates per group with present equipment status (STI, EPC, ABT, BI, RF, MSC, VSC)
- Risk analysis of LIU equipment:
Identify critical delivery path items (or already late) - Evaluate the impact on the shutdown activities
- Discuss mitigation (with agreed methodology)
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations
- Review readiness prospects and critical subsystems for selected highest risk/impact systems
- Preparation planning with present status (delivery, assembly, vacuum acceptance tests, pre-tests, etc… up to readiness for installation)
- Specify IST periods and dependencies on other groups/support
- Identification of specific technical an schedule risks and mitigations