Conveners
Session 3: LIU hardware and beam commissioning
- Alexander Huschauer (CERN)
- Verena Kain (CERN)
Session 3: LIU hardware and beam commissioning
- Verena Kain (CERN)
- Alexander Huschauer (CERN)
Alexander Huschauer
(CERN),
Verena Kain
(CERN)
15/02/2019, 08:40
o Keywords:
- BCWG, 2019/20 activities, organisation, responsibilities, commissioning phases
o Points to be addressed:
- Review of the 2018 BCWG activities and achievements
- Outline for activities in 2019/20
- Organisation, structure and responsibilities for 2019/20 activities and beyond
- Global planning to achieve LIU beam parameters.
- Introduction of different commissioning phases...
Delphine Jacquet
(CERN)
15/02/2019, 10:05
o Keywords:
- operational and controls aspects, scheduling, physics concepts, timing system, forum, beam instrumentation, performance monitoring, optimisation algorithms/machine learning
o Points to be addressed and questions to be answered:
- Discuss requirements and ideas to improve and facilitate operation after LS2
- Consider operational and controls aspects
- Discuss common...
Kevin Shing Bruce Li
(CERN)
15/02/2019, 11:25
o Points to be addressed:
- Detailed planning for pre-LS2 beam performance recovery according to the master schedule
- Define milestones for the different beam commissioning phases for LHC and non-LHC beams
- Details on commissioning of LIU equipment
- Hardware and software prerequisites
- Identify potential critical items/unknowns that could impact the schedule
- Implications of the CERN...
Gian Piero Di Giovanni
(CERN)
15/02/2019, 12:05
o Points to be addressed:
- Detailed planning for pre-LS2 beam performance recovery according to the master schedule
- Define milestones for the different beam commissioning phases for LHC and non-LHC beams
- Details on commissioning of LIU equipment
- Hardware and software prerequisites
- Identify potential critical items/unknowns that could impact the schedule
- Implications of the CERN...
Reyes Alemany Fernandez
(CERN)
15/02/2019, 12:25
o Points to be addressed:
- Detailed planning for for Linac3 and LEIR pre-LS2 beam performance recovery according to the master schedule
- Define milestones for the different beam commissioning phases
- Milestones for slip stacking
- Details on commissioning of LIU equipment
- Hardware and software prerequisites
- Identify potential critical items/unknowns that could impact the schedule
-...