GIF++ installation and schedule meeting
-
-
09:15
→
09:25
Review of last week operation & plans for this week 10m
Monday evening (≈ 4pm) : Problem with Argon line - connected to N2 by mistake.
Yesterday summary :
EP-DT - one cable pulled, needs floor opening.
(Right now CF4 line looks low pressure)Downstream :
ATLAS RPC - not yet back in the bunker
Upstream :
=========
ATLAS-MM : scans this week (details to be added later today)
Night time : 6.9 for one week
CMS-RPC : prefers 2.2, we see next week
EP-DT : needs 6.9, so see if they can move then to 5 meters (one day needed to check / filter scans)Downstream :
==========
CMS-DT : suffering from gas issue.
If chamber is OK, filters scan between 460-22, 2h in filter 100. finishing 16-17h
CMS-CSC : at filter 1 for 2h Friday morning (starting at 10h)Access tomorrow 9h30 for 30 minutes.
-
09:25
→
09:40
Mass Production Test Schedule 15m
Upstream field :
ATLAS-MM : SM2 flipped, SM1 closer to source, LM2 taken out yesterday - comes back next year Jan/Feb.
SM1 + SM2 one more week, then out until Jan.
starting from January 4 chambers per months - 2 / 4 chambers at the same time. ≈ for 1 year.ALICE TCP : 6 chambers, (3 big, 3 small) - 2 at the same time, swap takes 45 minutes.
currently on hold, restarting in two weeks (then mostly unshadowed)
Total 20-30 (aiming for 6 per week, 1 day flushing, few hours for testing) - 5 weeksDownstream :
CMS-DT 1/15 campaign until early January.
ATLAS - sTGC : 5-6 chambers should arrive beginning of mid January - half an hour for each chamber(might be better compatible with upstream) - 09:40 → 09:50
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========CERN wide power cut on 19.12 - 6h.
Ongoing Projects :
NEW retrieval of TIMBER values : Work in progress, but already available in beta version
https://epdtdi-pytimber.web.cern.ch/app/gifpp (also linked from main GIF page.Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only -
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2018 5m
Guidelines for filling in IMPACT requests
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2018. (All current IMPACTS will expire at Saturday 23.December)
Special IMPACT needed for Christmas Closure.
-
-