PSB Commissioning Meeting #8
Communications:
- LIU Day is planned for the 14-15 February
- A presentation of the full post-LS2 planning until Nov 2020 is expected
- Explicit request to provide readiness for fixed target physics
Deadline:
- The document must be ready by the 31st January 2019
- Before the end of the year we should agree on tentative dates for the fixed target
=====================================================================================
Questions concerning Linac4 RF and longitudinal painting:
1) No longitudinal painting:
a. Different energy spread and injected longitudinal emittance per user: needed (we have to answer)? Possible (Linac4 RF)?
b. For same user, assuming need for different number of injection turns per ring: any need to adapt the momentum spread and injected longitudinal emittance depending on number of injection turns?
2) Longitudinal painting:
a. Different energy spread, energy swing and injected longitudinal emittance per user: needed (we have to answer)? Possible(Linac4 RF)?
b. For same user, assuming need for different number of injection turns per ring:
i. Ideally we would like to be able to have, per each ring, an optimum longitudinal painting: different number of turns for the energy swing (different momentum spread)
ii. If not possible, forced to adapt the longitudinal painting to the scheme of the ring where the minimum number of injection turns is required, correct?