    • 1
      Review of last week operation & plans for this week

      Weekly summary and plan for the next week :

       ------------------------

      ALICE :  2 chamber to test, Friday morning.  8h30 - 1h test + short access + 1h + short access
                       Next week 4 small chambers expected.

      ATLAS-MM :  1 chamber SM1 (module6), access during Friday (shadow of ALICE)
                               test starting on Monday : Scan 2h each day of week (22  to 4.6), starting 9h
                              GC test successful, will reuse it end of next week.
                              Training with Beatrice pending.

      EP-DT2  : Starting Friday : afternoon 3h scan (filter 100 stable)
                       + whole next week starting on 14h

      Otherwise : 4.6 filter for most of the week.

      EcoGas  - last chamber installed, staying on CMS-RPC gas mixture.
                          

      CMS-RPC :  Scan this afternoon 6.9  - 2h starting at 13h

                           Upcoming - 1 week test for FE electronics with priority for the access / bunker
                           Cosmic run with Scintillator / filter 2.2. or 6.9 - to be defined. Around ≈ 20. March.
                           New chambers arriving 20-25.03  - IMPACT to be done

      sTGC Production :  return Mid-March

      sTGC : 3h source scan after CMS-RPC (≈15h)
                    One hour access / together with ALICE on Monday.

      Access for Friday around 9h for 1h
       



      CMS-GEM 1&2 : Happy


      EP-DT1 : need some access (30 min) after the meeting to check some issue with Ar supply 

      ATLAS-RPC  : No special request for this week.

      CMS-DT MB 1&2  :   No comment.

      LHCb : preparation to exchange chamber.  Installing it next Wednesday.

      CMS-CSC: Continuing radiation.
                         Enjoing the stable conditions from EP-DT2.

    • 2
      Mass Production Tests & Long Term Campaigns - General Items

      General planning for long term campaigns.

    • 3
      New requests for tests at GIF

      introduction, goal of the test, plan, needs

       

      Upcoming BE-BI : test of  XBPF in 100Gy steps. Starting soon.

    • 4
      Infrastructure & Upgrades to the Facility

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • a) LS2 restrictions & interventions
      • b) Bunker Extension Project

        News about the ongoing bunker extension

        Bunker extension :

        ==============

        Bunker layout frozen, work started already.

        Next step : Re-arrange wall behind electrical switchboard 
        -> Announce power cut NEXT WEDNESDAY 13.02 at 9h for less than 2h.                                                                                   ->Due to a problem with a breaker upstream, the facility couldn't be restarted before 03.40 pm

        Currently estimated start : Either early July or early September.  (before or after August)
        If we want July, we have to push now.

      • c) Cosmic Trigger
    • 5
      Announcements

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • a) IMPACTS for 2019

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • b) New Announcements
      • c) AOB

        Issue with ligth.  Button near access door should enable the light for additional 2h.
        We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLE

        Locked door on Saleve side.
        Proposal top remove the cylinder to avoid the guard locking the door during night times.  -> Cylinder HAS BEEN REMOVED