GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------CO2 Tue 16.4 : strange behaviour of CO2. (drop of CO2 for a few seconds)
Local "Power cut" not understood yet. Investigation ongoing.
Bunker Temperature : 1 degree drift. Linked to the the cooling water maintenance - to be finished end of THIS week.ALICE : Done !
ATLAS - sTGC : QS1 arrived. QS3 tested and removed. Today 1 QS1 + 1 QS3 to be installed.
Mass production test : planned to be in front of CMS-SCS downstream or on the side.
We check today after lunch.ATLAS-MM : SM1-M3 installed in bunker at 2.9m upstream - another week of irradiation planned.
LM1-M3 to be removed Tuesday afternoon. SM2 to go in.
Universal trolley to arrive mid May. Tentative to be placed in current CMS-DT location.
Moving to premixed bottles.EP-DT1: Fine. Radiating.
EP-DT2 : Measurement ongoing. No special request for this week.
EcoGas - Running dedicated mixer. HF4 bottle delivery to be checked.
CMS-RPC : Problem with deconnecting gas line. FG alarm triggered. FB called. Source off for ≈ 3h.
One trolleys for longevity test and the other for testing the electronics in order to launch the mass production. One installed, one (cosmic trigger) to be installed next week (Thursday). ISEC visit requested.
Gas flow needs to be checked, as we are on the limit. Shared with ATLAS-RPC. Gas flow reduced a bit. To be discussed with EP-DT-FS.CMS-GEM 1&2 : 2 is Happy, some problem one GEM 1 (crate outside was failing) - will be fixed with arrival of new chamber. Some delays.
ATLAS-RPC : BIS no update, some problems with truck from Italy. Maybe in 2 weeks. No report - no presence.
CMS-DT MB 1&2 : Start of de-cabling next Tuesday afternoon.
Removal planned 8th of May.LHCb : No update.
CMS-CSC: Continuing radiation and recovering the setups from the preparation area.
==========================================================
NEXT TUESDAY : Afternoon additional access day.
Weekly Planning : UPSTREAM
Default filter settings : 2.2
Thursday (today): after 18h ATLAS-MM 2h scan 10-2.2
Friday : EcoGas : 13h 3 scan 6.9/22/2.2 (1h30 each)
CMS - RPC : source scan with ABS = 6.9 in shadow of EcoGas
ATLAS -sTGC : morning 1h scan filter 1 (or downstream)Saturday : ATLAS -sTGC : morning 1h scan filter 1 (or downstream)
Sunday : EcoGas GC needed 6.9 or 22 17h-next morning
Monday : ATLAS -sTGC : morning 1h scan filter 1 (or downstream)
EcoGas GC needed 6.9 or 22 17h-next morningTuesday : ATLAS -MM (morning) 4-5h scan, 1h each from 10-1 attenuation
Wednesday:
Thursday : ATLAS -MM (morning) 4-5h scan, 1h each from 10-1 attenuation
-------------------------------------------------------------------------------------------------------
Weekly Planning : DOWNSTREAM
Default filter settings : 1
Thursday :
Friday :
Saturday :
Sunday :
Monday :
Tuesday :
Wednesday:
-------------------------------------------------------------------------------------------------------
Access Requests :
Thursday:
- 09:35 → 09:40
- 09:40 → 09:50
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Cleaning of DCS and installation of UPS : to be scheduled.
Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
Bunker Extension Project 10m
News about the ongoing bunker extension
-
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
AOB 5m
Issue with ligth. Button near access door should enable the light for additional 2h.
We plan to keep the light over the GIF area active in the near future (change by EN-EL needed) -> NOT FEASABLELocked door on Saleve side.
Proposal top remove the cylinder to avoid the guard locking the door during night times. -> Cylinder HAS BEEN REMOVED
-
-