GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 → 09:35
      Review of last week operation & plans for this week 20m

      User Reports / Overview :

      ----------------------------------

      ATLAS - sTGC : 2 QS1 tested at GIF++ and sent to bldg. 180
                                  3 QS3 arrived 1 tested  and other 2 to be tested during this week.                                                                                3 QS3P will arrive at GIF++ tomorrow June 21st and has to be tested before the bunker                                            extention will start. In principle if everything goes well the test of the chambers is over on                                        Thursday June 27th.  

      ATLAS-MM :  SM1-M11, SM2-M8 will stay till June 26th when everything will go out. Then, LM2-M4 will be                             installed and will stay till July 1st.
                              

      EP-DT1:  Oxygen (peak suspected), but now everything went back to normal. Small problem with the pump of                      the close loop system. Everything will be removed already on Wed 26th

      EP-DT2 : Test on the stability of gas systems. Dismountling will start already on Wed 26th

      EcoGas :  Test on going in parallel with CMS-RPC electronic test.

      CMS-RPC :  Trolley for testing the electronics is installed. Cosmics with background. Some modification has been done in order to shield as much as possible the PMTs 
                            22-46 filter range with 10h scans. as much as possible.
                            1 week program. 46-4.6 for 6h each.  (maybe a few hours 2.2)
                            For the other trolleys 2.2 requested.
                            In principle ready to start to dismount on Wed 26th.

      CMS-GEM 1&2 : GEM 2 will dismount everything on July 1st                                                                                                                  GEM 1: OFF

      ATLAS-RPC :  No reports for both R&D and BIS setups.                

      LHCb :  Fine.

      CMS-CSC:  Oxygen cell changed. Still to see if needed to be re-calibrated. Roberto is taking care. Some troubles                        with electronic boards, that have been changed yesterday and now everything works fine. 4h source                        OFF needed today from 3pm   
                          Plan to irradiate till July 1st.                                                                                                                                            

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe

      UPSTREAM : Default filter settings :  2.2 

      DOWNSTREAM :  Default filter settings :  1

      -------------------------------------------------------------------------------------------------------

       

    • 09:35 → 09:40
      Long Term Planing - General Items 5m

      Irradiator Maintenance : Week 29

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

       https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex 

       https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N

       

      ---------------------------------------------------------

      Next Annual User Meeting :  Proposed day TUESDAY 10.09.2019
      Please let us know if there are particular bad days (ATLAS/CMS weeks etc)

       

    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      Gas recuperation system to be installed (end of June) - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.

    • 09:50 → 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Cleaning of DCS and installation of UPS : to be scheduled.

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

    • 10:00 → 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • New Announcements 5m
      • AOB 5m

        Issue with ligth.  Button near access door should enable the light for additional 2h.