GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------
ATLAS - sTGC : 2 QS1 tested at GIF++ and sent to bldg. 180
3 QS3 arrived 1 tested and other 2 to be tested during this week. 3 QS3P will arrive at GIF++ tomorrow June 21st and has to be tested before the bunker extention will start. In principle if everything goes well the test of the chambers is over on Thursday June 27th.ATLAS-MM : SM1-M11, SM2-M8 will stay till June 26th when everything will go out. Then, LM2-M4 will be installed and will stay till July 1st.
EP-DT1: Oxygen (peak suspected), but now everything went back to normal. Small problem with the pump of the close loop system. Everything will be removed already on Wed 26th
EP-DT2 : Test on the stability of gas systems. Dismountling will start already on Wed 26th
EcoGas : Test on going in parallel with CMS-RPC electronic test.
CMS-RPC : Trolley for testing the electronics is installed. Cosmics with background. Some modification has been done in order to shield as much as possible the PMTs
22-46 filter range with 10h scans. as much as possible.
1 week program. 46-4.6 for 6h each. (maybe a few hours 2.2)
For the other trolleys 2.2 requested.
In principle ready to start to dismount on Wed 26th.CMS-GEM 1&2 : GEM 2 will dismount everything on July 1st GEM 1: OFF
ATLAS-RPC : No reports for both R&D and BIS setups.
LHCb : Fine.
CMS-CSC: Oxygen cell changed. Still to see if needed to be re-calibrated. Roberto is taking care. Some troubles with electronic boards, that have been changed yesterday and now everything works fine. 4h source OFF needed today from 3pm
Plan to irradiate till July 1st.==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
Irradiator Maintenance : Week 29
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
Next Annual User Meeting : Proposed day TUESDAY 10.09.2019
Please let us know if there are particular bad days (ATLAS/CMS weeks etc) - 09:40 → 09:50
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Cleaning of DCS and installation of UPS : to be scheduled.
Ongoing Projects :
=============Correction of Irradiator Signals after power cut.
Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.PyTIMBER :
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
Bunker Extension Project 10m
News about the ongoing bunker extension
-
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).NEW IMPACT needed for 2019 !
-
AOB 5m
-
-