B163 upgrade - Progress meeting
Actions: update done during the meeting (see action follow-up)
- TE-MSC reporting: see presentations
- TE-MPE reporting:
- EE - Secheron almost ready for the delivery at the beginning of September 2019. The existing system shall be disconnected. After installation of the new system, one test will be done to check that all is correct and then the old one will be thrown. Dump resistors are at CERN
- TE-CRG reporting:
- B165 is operational. All the functional modes have been tested. Beginning of September it is foreseen to prepare the work on N2 circuit in advance.
- B163 - design is frozen, manufacturing started.
- Jumbo cylinders at CERN bat the end of August 2019
- Integration: see presentation