B163 upgrade - Progress meeting
-
-
14:00
→
14:15
Action follow-up 15mSpeaker: Germana Riddone (CERN)
ACTIONS FROM THE MEETING ON 17.07.2019
1. F2 cryostat interfaces: EN-MME discussed with TE-CRG, problem with welding of inner tubes, planning and cost impact under evaluation at TE-CRG (deadline Mid of August 2019).
2. EN-MME will ask for an ad-hoc scan of the pit (follow-up by N. Joannon)
3. F2 pit: the vessel support feet to be replaced (action TE-MSC)
4. F2 pit: change pump, the current one is not compatible with the F2 cryostat . C. Barth to contact EN-CV
5. Instrumentation for F1 - prepare list from extraction of the TE-CRG database C. Barth will do the follow-up.
6. Integration: update model with integration of warm piping (A. Lees and N. Joannon)
7. Integration: send the model to EN-EL and ask for feedback (N. Joannon)
-
14:15
→
14:35
Update on Fresca2 cryostat design and production (inc. planning) 20mSpeaker: Arnaud Vande Craen (CERN)
-
14:35
→
14:45
Update on insert sample 10mSpeaker: Christian Barth (CERN)
- 14:45 → 14:55
- 14:55 → 15:10
-
15:10
→
15:20
Update on the cryogenic system and planning 10mSpeaker: Andrew John Lees (CERN)
-
15:20
→
15:30
Fresca 2 integration: status and issues 10mSpeaker: Nicolas Joannon
-
15:30
→
15:40
Conclusions 10m
-