Confirm with Luca Bottura the presence of a WP with EN-MME to clarify interfaces and responsibilities (G. Riddone)
F2 pit: the vessel support feet to be replaced (Ch. Barth)
F2 pit: change pump, the current one is not compatible with the F2 cryostat. Contact EN-CV (Ch. Barth)
Instrumentation for F1 - prepare list from extraction of the TE-CRG database C. Barth will do the follow-up. A meeting is scheduled with A. Lees in W38 (Ch. Barth)
Planning: to provide the shut-down planning to A. Ballarino (A. Lees)
F2 cost estimate: to contact F. Bertinelli to ask for cost estimate and planning consolidation (G. Riddone)
PID: no comments from A. Vande Craen, to be approved (G. Riddone)
F2 main interfaces: modification of interfaces drawings to take into account 20 mm increase in diameter of the thermal shield (A. Lees)
F2 GH2 interface: proposed EN-MME modification to be confirmed (A. Vande Craen)
Integration: instrumentation racks to be integrated (N. Joannon)