GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 → 09:35
      Review of last week operation & plans for this week 20m

      Plan for first week of restart :

      • Monday : opening of floor, checking and re-routing cables, setups to arrive in preparation area
      • Tuesday : installation of setups inside the bunker, connection to gas systems
      • Wednesday : Finalizing, restart of Irradiator in the late afternoon

                                                                                        

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe  (updated next meeting)

      UPSTREAM : Default filter settings :  -

      DOWNSTREAM :  Default filter settings :   -

      -------------------------------------------------------------------------------------------------------

       

    • 09:35 → 09:40
      Long Term Planing - General Items 5m

      Annual User Meeting :  TUESDAY 10.09.2019

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

       https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex 

       https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N

      ---------------------------------------------------------

      To be scheduled : Stop of Gas supply for 2-3 days : to be scheduled (end of the year / beginning of next year)

    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      Gas recuperation system to be installed (end of July) - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.

    • 09:50 → 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      New Items :
      ==========

      Cleaning of DCS and installation of UPS : to be scheduled.

      Ongoing Projects :
      =============

      Correction of Irradiator Signals after power cut.
      Since installation of UPS, the Irradiator signals UNSAFE after a power cut, independently if the source was ON or OFF at the time. In reality, source will always be in safe position after power cut. Power cycle controls in control room to get correct status.

       

      PyTIMBER :

          Additional values need to be collected/republished ?
              - REMUS  - to be included in GIF Display
              - XTDV - to be included in pytimber only

      • LS2 restrictions & interventions 5m
      • Cosmic Trigger 10m
    • 10:00 → 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

         

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

        NEW IMPACT needed for 2019 !

      • New Announcements 5m
      • AOB 5m