GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------
ATLAS - sTGC : ready for the installation and test of the new chambers arrived. 2 setup ready to be installed upstream.ATLAS-MM : still need some time to finish with the installation but everything will be ready by the end of the day. 2 independent setup will be installed downstream .
EP-DT1: 2 setup installed downstream. Ready to start testing
EP-DT2 : Out of bunker
EcoGas : 1 Setup with multiples chambers installed upstream and ready to start testing
CMS-RPC : Setup installed upstream and ready to start testing
CMS-GEM 1: Out of bunker. No report
ATLAS-RPC : Out of bunker. No reportLHCb : The analysis on the chamber irradiated at GIF++ is starting. More news to come.
CMS-CSC: Out of bunker. No report
* Gas supply: all the supply are now open again. There will be a small interruption this afternoon at 2.30 pm on the isobutane line. The cut should be less than half an hour.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : starting with 1 and check if it is feasible to use it all the time
DOWNSTREAM : Default filter settings : starting with 1 and check if it is feasible to use it all the time
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
Annual User Meeting : TUESDAY 10.09.2019
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
To be scheduled : Stop of Gas supply for 2-3 days : to be scheduled (end of the year / beginning of next year)
- 09:40 → 09:50
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Cleaning of DCS and installation of UPS : to be scheduled.
Ongoing Projects :
=============PyTIMBER :
New improved data plotting and data export under development - will be moved to production site soon
Additional values need to be collected/republished ?
- REMUS - to be included in GIF Display
- XTDV - to be included in pytimber only-
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-