09:15
→
09:35
Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------
ATLAS - sTGC : 2 setup installed upstream - one with 4 chambers (2 inside, 2 outside), and second setup with 2 chambers.ATLAS-MM : 2 setups installed, one staying for long term irradiation (≈ October).
Still using premixed bottles. Tomorrow, morning removal of the 2 chambers on universal trolley.
Access planed 9h30 for ≈ 1h.CMS-CSC: Re-installation next Wednesday. Both the setup close to the source, and the second in the far corner.
Potential long term plan: maybe setup from downstream wall to be moved to upstream wall.
GC requested for next week.EP-DT1: Measurements during the nights - stable radiation - filter 1. 5 minute access needed at beginning 18h and end 8h30.
EP-DT2 : 2 chambers installed in setup, around 6m upstream.
EcoGas : 1 Setup with multiples chambers installed upstream and ready to start testing
installed in CMS-RPC trolley 3.CMS-RPC : 2 setup installed (trolley 3 and trolley 1) upstream and ready to start testing
New electronics setup might come back next week, in front of trolley 3.CMS-GEM 1: Out of bunker. Maybe back after summer.
ATLAS-RPC : Out of bunker. No report.
LHCb : The analysis on the chamber irradiated at GIF++ is starting. More news to come.
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
Annual User Meeting : TUESDAY 10.09.2019
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
To be scheduled : Stop of Gas supply for 2-3 days : to be scheduled (end of the year / beginning of next year)
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)New Items :
==========Cleaning of DCS and installation of UPS : to be scheduled.
Ongoing Projects :
=============PyTIMBER :
New improved data plotting and data export under development - will be moved to production site soon.
Please check it at http://instancecc7.cern.ch:8080/app/gifpp
Additional values need to be collected/republished :
- REMUS - PAXN1646 and PAXN1647 to be included in GifCS
- H4C - Chain Beam Veto, Chain Manual Veto, Chain Radiation Veto
- Zone 154 : PPG and search status to be included
- CESAR : XTDV - to be included in pytimber only ?
-
Cosmic Trigger 10m
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-