Expected quench levels of the machine without beam: starting at 7 Tev ?

24 Jan 2006, 16:40
15m
L'Esplanade du Lac, Divonne-les-Bains

L'Esplanade du Lac, Divonne-les-Bains

Speaker

Pierre Pugnat (AT/MTM)

Description

The quench training performance of about 900 LHC main dipoles and 200 main quadrupoles cold tested to date will be presented and commented. From these results an estimate of the number of quenches that could be required to operate the whole machine at nominal energy will be presented without considering beam loss effects. The energy level at which the machine could be operated without being disturbed by training quenches at the early phase of the commissioning will also be addressed. The missing and required information necessary to improve these predictions will be pointed out.