GIF++ installation and schedule meeting

Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 09:35
      Review of last week operation & plans for this week 20m

      User Reports / Overview :

      ----------------------------------

      ATLAS - sTGC :  2 QL3 tested and removed from the bunker.  2 QL2 types to be installed on Monday. Test on Tuesday. More chambers coming mid-december. Frequent access will be needed.

      ATLAS-MM :   One chamber installed for long term irradiation test near source LM2 (Pos,D02)
      Gas studies, long term.  2 chambers in setup behind CMS-CSC installed yesterday

      CMS-CSC: Irradiating sing last week. Friday afternoon - requesting stable conditions.
      Setup from preparation area to be moved (bunker upstream or Bld. 904).

      EP-DT1:  Stable conditions default 1. Fluoride measurements done. 
      Setup moved of 25 cm closer to the source.  Until Christmas.

      EP-DT2 : Request to have the default value 2.2 in upstream.
      GC would be needed for the next 2 weeks.

      CMS-DT: Rails back installed. Long one fixed to floor, other to be done.
      Electronic racks needed mid-November. Chamber expected to be installed end of year.
      Field mapping at far end of bunker planned for Thursday December 05th afternoon.

      EcoGas :  Running, filter scans planned.

      CMS-RPC :  iRPC and Trolley 1& 3 in bunker.  Small trolley with iRPC installed yesterday. 

      ATLAS-RPC :  Small prototype installed on October 23rd still taking data.
      Big setup with ATL-RPC gap will be installed next week on Wed DEC 04th.

      LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
      Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.     

       

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 

      UPSTREAM : Default filter settings :  2.2

      DOWNSTREAM :  Default filter settings :  1

      -------------------------------------------------------------------------------------------------------

       

    • 09:35 09:40
      Long Term Planing - General Items 5m

      ---------------------------------------------------------

      Gas usage during Christmas to be announced.
       

       

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

       https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex 

       https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N

      ---------------------------------------------------------

      To be scheduled : Stop of Gas supply for 2-3 days : to be scheduled (end of the year / beginning of next year)

      ---------------------------------------------------------

      Next Irradiator maintenance :  Proposal - January after Christmas Closure

    • 09:40 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      BLM measuring campaign announced / ≈ 100 BLM, 3 days approx.  First half of 2020 ?

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

       

      Bulgaria academy of science -> testing of new type of radiation monitor system 

       

       

      A new setup of ALICE-RPC will come. More news in coming weeks.

    • 09:50 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      Need to install AUL in far end of bunker. To be scheduled.

      • LS2 restrictions & interventions 5m

        Upcoming :
        =============

        PRIMARY & RAW WATER 2/2

        Status

        • –  CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.

        • –  BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

        • –  BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

      • Cosmic Trigger 10m
    • 10:00 10:30
      Announcements 30m

      You can subscribe to the calendar with the following link (to be added in you calendar application)
      http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics

      • IMPACTS for 2019 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • New Announcements 5m
      • AOB 5m