Review of last week operation & plans for this week 20m
User Reports / Overview :
----------------------------------
ATLAS - sTGC : Currently no chamber installed. 8 Chambers should arrive tomorrow.
2 needs to be tested on Saturday. 1 QL1 is critical to be tested & installed.
CO2 flow issues during the last months. Interlock changed, currently working, but needs follow up.ATLAS-MM : 2 chambers in setup behind CMS-CSC installed - will leave for Christmas.
One chamber installed for long term irradiation test near source LM2 (Pos,D02).
Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
Will be clarified in the coming weeks.CMS-CSC: Irradiating sing last week. Friday afternoon - requesting stable conditions.
Setup from preparation area to be moved (bunker upstream or Bld. 904).EP-DT1: Setup moved of 25 cm closer to the source. Until Christmas.
EP-DT2 : Request to have the default value 2.2 in upstream.
GC would be needed for the next 2 weeks.CMS-DT: Rails back installed. Long one fixed to floor, other to be done.
Electronic racks needed mid-November. Chamber expected to be installed around February.
EcoGas : Will be switched off for Christmas / no flushing.
CMS-RPC : iRPC and Trolley 1& 3 in bunker. Small trolley with iRPC installed.
ATLAS-RPC : Small prototype installed on October 23rd still taking data.
Big setup with ATL-RPC gap will be installed next week on Wed DEC 04th.LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
---------------------------------------------------------
Stop of Gas supply for 7.01 to 10.01 !
Gas usage during Christmas announced.
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
---------------------------------------------------------
Next Irradiator maintenance : Proposal - January after Christmas Closure.
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
BLM measuring campaign announced / ≈ 100 BLM, 3 days approx. First half of 2020 ?
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
-
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)-
LS2 restrictions & interventions 5m
Upcoming :
=============PRIMARY & RAW WATER 2/2
• Status
-
– CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.
-
– BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
– BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
-
Cosmic Trigger 10m
-
-
10:00
→
10:30
Announcements 30m
You can subscribe to the calendar with the following link (to be added in you calendar application)
http://mmm.cern.ch/owa/calendar/fad3257aa1c74520bd63ea8f3d126245@cern.ch/b2719d8034af4743a801cdd73f3b969315436460478832573385/calendar.ics-
IMPACTS for 2019 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-
09:15
→
09:35