    • 09:15 → 09:35
      Review of last week operation & plans for this week 20m

      Remember to put e-log messages when you turn ON/OFF the source, change filter etc.

      User Reports / Overview :

      ----------------------------------

      ATLAS-MM :  Long term chamber installed (LM2 (Pos,D02)), will stay for a few months.

      Wednesday, 2 new large detectors to installed normally.
      New detectors are expected every Wednesday. Running from pre-mixed bottle (bank).

      Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
      Will be clarified in the coming weeks.

      Katerina checked the cables/pipes and there is the possibility to move her setup close to the source by 50cm.
      In three weeks time, asking EP-DT to move a bit closer to the source, to allow using a small sTGC chamber as monitor.

      ATLAS - sTGC :  2 chambers installed inside bunker. We now have chambers for several weeks to test. Details can be seen in the teamup schedule. Currently agreed to host 2-3 boxes in preparation area.

      CMS-CSC:  One setup back in normal position. 
      Setup from preparation area to be moved in Bld. 904 on Friday.

      EP-DT1:   Discussion if possible to move closer. For the moment is fine. No irradiation till mid-March, only source scan every Wednesday. From beginning of March it would be nice to install another setup. Position and installation to check together in the bunker directly.

      EP-DT2 :  Irradiating. Request to have the default value 2.2 upstream as soon as possible. 

      CMS-DT: Rails back installed. Electronic racks to be finished. Cosmic run started on Wed 29th
      Chambers expected to be installed around Mid March.

      EcoGas :  Running.

      CMS-RPC :  iRPC will stay for another month. 
      Trolley 1& 3 in bunker. 
      For this week 4.6 would be preferred. Some scans with higher absorption 6.9/10/46000 for short periods.

      Cosmic trigger activity to continuing. For today there is the need to have a long source scan with different filter attenuation as reported in teamup. So far good results. 

      ATLAS-RPC:   One setup, from BIS78 production, back in the bunker on Monday, profiting of ATL-sTGC access. ATL-RPC high rate small prototype coming end of February.

      LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
      Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.    

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 

      UPSTREAM : Default filter settings :  4.6

      DOWNSTREAM :  Default filter settings :  1

      -------------------------------------------------------------------------------------------------------

       

    • 09:35 → 09:40
      Long Term Planing - General Items 5m

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ATL-RPC high rate prototype

      BLM measuring campaign announced / ≈ 100 BLM, 3 days approx.  First half of 2020 ?

      Bulgaria academy of science -> testing of new type of radiation monitor system

      A new setup of ALICE-RPC will come. More news in coming weeks.

      MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about June this year.

      Lab on Fiber (LOF) dosimeter

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

    • 09:50 → 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      EHN1 AUG Test scheduled for beginning of April.

      Need to install AUL in far end of bunker. To be scheduled.

      Need to install a gas patch panel in the upstream area. To be scheduled.

      New cable installed for the MAD. 

      • LS2 restrictions & interventions 5m

        Ongoing :
        =============

        PRIMARY & RAW WATER 2/2

        • Status

        • –  CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.

        • –  BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

        • –  BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

      • Cosmic Trigger 10m
    • 10:00 → 10:30
      Announcements 30m
      • IMPACTS for 2020 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • New Announcements 5m
      • AOB 5m

        Electrical inspection passed yesterday. Only few comments. Report to come and after, a check with all of you will be needed.