GIF++ installation and schedule meeting

→ Europe/Zurich
892/1-B09 (CERN)

892/1-B09

CERN

30
Show room on map
Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN), Federico Ravotti (CERN)
There are minutes attached to this event. Show them.
    • 09:15 → 09:35
      Review of last week operation & plans for this week 20m

      Remember to put e-log messages when you turn ON/OFF the source, change filter etc.

      User Reports / Overview :

      ----------------------------------

      ATLAS-MM : 

      the plan for this week and next one is the following:

      - yesterday 2 detectors entered (LM2 M16 and LM1 M15) ==> They will stay up to next wednesday, then other two will enter 

      - Long term LM2 M7 detector will stay up to next week wednesday, then it may be removed (we have to decide anyhow, it could also stay 1 week more)

      - Scan requests already in TeamUp.

      - Next wednesday the new gas bank will be installed and  the "old" one will be move out 

      - filed mapping to organise for next week

      Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
      Will be clarified in the coming weeks.

      Katerina checked the cables/pipes and there is the possibility to move her setup close to the source by 50cm.
      Trying to do the swap already next Wednesday 19th. 

      ATLAS - sTGC :  2 chambers installed inside bunker. We now have chambers for several weeks to test. Details can be seen in the teamup schedule. Currently agreed to host 2-3 boxes in preparation area.

      CMS-CSC:  One setup back in normal position. 
      Setup from preparation area moved in Bld. 904.

      EP-DT1:   Discussion if possible to move closer. For the moment is fine. No irradiation till mid-March, only source scan every Wednesday. From beginning of March it would be nice to install another setup. Position and installation to check together in the bunker directly.

      EP-DT2 :  Irradiating. Request to have the default value 2.2 upstream as soon as possible. 

      CMS-DT: Rails installed back. Electronic racks to be finished. Cosmic run started on Wed Jan 29th
      Chambers expected to be installed around mid March. 

      EcoGas :  Running. Need of stable conditions

      CMS-RPC :  iRPC will stay for another month. 
      Trolley 1& 3 in bunker. 
      Measurements with filter 46000 are done. 

      Cosmic trigger activity to continuing. So far good results. 

      ATLAS-RPC:   One setup, from BIS78 production, back in the bunker on Monday, profiting of ATL-sTGC access. ATL-RPC high rate small prototype coming end of February. Access needed on February 17th for removing the setup.

      LHCb : working on the irradiated prototypes removed from GIF++ some months ago.
      Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.    

      ==========================================================

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 

      UPSTREAM : Default filter settings :  2.2

      DOWNSTREAM :  Default filter settings :  1

      -------------------------------------------------------------------------------------------------------

       

    • 09:35 → 09:40
      Long Term Planing - General Items 5m

      ---------------------------------------------------------

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.
       

    • 09:40 → 09:50
      New requests for tests at GIF 10m

      introduction, goal of the test, plan, needs

      ATL-RPC high rate prototype

      BLM measuring campaign announced / ≈ 100 BLM, 2 days approx.  Most probably a good period would be from March 09th. 

      Bulgaria academy of science -> testing of new type of radiation monitor system

      A new setup of ALICE-RPC will come. More news in coming weeks.

      MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about June this year.

      Lab on Fiber (LOF) dosimeter

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

    • 09:50 → 10:00
      Infrastructure & Upgrades to the Facility 10m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      EHN1 AUG Test scheduled for beginning of April.

       

      Need to install a gas patch panel in the upstream area. To be scheduled.

       

      AUL and multi-sockets test on WED 19th 

      Annual maintenance EHN1 gas detection system on WED 19th - cutting all the gas for a  couples of minutes

      • LS2 restrictions & interventions 5m

        Ongoing :
        =============

        PRIMARY & RAW WATER 2/2

        • Status

        • –  CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.

        • –  BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

        • –  BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.

      • Cosmic Trigger 10m
    • 10:00 → 10:30
      Announcements 30m
      • IMPACTS for 2020 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • New Announcements 5m
      • AOB 5m

        Electrical inspection passed yesterday. Only few comments. Report to come and after, a check with all of you will be needed.