GIF++ installation and schedule meeting
-
-
09:15
→
09:35
Review of last week operation & plans for this week 20m
Remember to put e-log messages when you turn ON/OFF the source, change filter etc.
User Reports / Overview :
Stop of CO2 on Monday morning.
----------------------------------
ATLAS-MM :the plan for this week and next one is the following:
- Long term LM2 M7 detector will stay up to 04.03, then removed.
≈ 1 week later new long term (≈ 3 months) SM1- 2 detectors normally tested for one week in position D3 - D4 for the upcoming future.
- Scan requests already in TeamUp.
- filed mapping to organise for next week
Discussion : Possible installation of 1 full assembled sector in Upstream. ≈ Feb. for 2 months.
Will be clarified in the coming weeks.Katerina checked the cables/pipes and there is the possibility to move her setup close to the source by 50cm.
ATLAS - sTGC : 1 chambers installed inside bunker. We now have chambers for several weeks to test. Details can be seen in the teamup schedule. Currently agreed to host 2-3 boxes in preparation area.
CMS-CSC: (not present) One setup back in normal position.
Setup from preparation area moved in Bld. 904.EP-DT1: (not present) Discussion if possible to move closer. For the moment is fine. No irradiation till mid-March, only source scan every Wednesday. From beginning of March it would be nice to install another setup. Position and installation to check together in the bunker directly.
EP-DT2 : (not present) Irradiating. Request to have the default value 2.2 upstream as soon as possible.
CMS-DT: Rails installed back. Electronic racks to be finished. Cosmic run started on Wed Jan 29th
Work will intensify around mid March. Chambers to be installed in the bunker end of March. Date to be fixed.EcoGas : (not present) Running. Need of stable conditions
CMS-RPC : (not present) iRPC will stay for another month.
Trolley 1& 3 in bunker. Measurements with filter 46000 are done.Cosmic trigger activity to continuing. So far good results.
ATLAS-RPC: (not present) One setup, from BIS78 production, back in the bunker on Monday, profiting of ATL-sTGC access. ATL-RPC high rate small prototype coming end of February. Access needed on February 17th for removing the setup.
LHCb : (not present) working on the irradiated prototypes removed from GIF++ some months ago.
Will be back in GIF++ most probably next year. A standalone gas line/supply will be needed this time.==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 4.6 until Monday - 2.2 else
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
-
09:35
→
09:40
Long Term Planing - General Items 5m
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
-
09:40
→
09:50
New requests for tests at GIF 10m
introduction, goal of the test, plan, needs
ATL-RPC high rate prototype
BLM measuring campaign announced / ≈ 100 BLM, 2 days approx. Most probably a good period would be from March 09th.
Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
MPI Munich would like to perform ageing tests of sMDT chambers in the GIF++ starting from about June this year.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) -
09:50
→
10:00
Infrastructure & Upgrades to the Facility 10m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)-
LS2 restrictions & interventions 5m
Ongoing :
=============PRIMARY & RAW WATER 2/2
• Status
-
– CT2 (Primary water) : Running until 18th Oct 19 and will be stopped until 15th Apr 20.
-
– BA81 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
– BA82 (Raw water) : Running until 17th Oct 19 and will be stopped until 17th Apr 20.
-
-
Cosmic Trigger 10m
-
-
10:00
→
10:30
Announcements 30m
-
IMPACTS for 2020 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
-
-