LIU-SPS Machine Coordination Meeting 25/3/2020

Present: Andy Butterworth, Anthony Rey, Brennan Goddard, David Mcfarlane, Elena Chapochnikova, Eric Veyrunes, Fabio Follin, Francesco Maria Velotti, Frank Gerigk, Giulia Papotti , Hannes Bartosik, Ivan Karpov, James Ridewood, Johan Dalla-Costa, Kevin Shing Bruce Li, Lars Jensen, Marine Gourber-Pace, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Yannick Le Borgne. 

Matters arising

Eric and Elena 

Dry runs and test progress news (Kevin/Verena)

FGCs, information yesterday, will be ready 2-3 weeks after the restart, so everything that was foreseen for this week will be postponed, need to be replanned.

One more thing we can do is to do the upload of the verified optics. Hannes is following this with Sonia, might come in a few weeks.

Check lists of ISTs (James)

Checklist tool has been improved

ISTs now included in the SPS HWC checklists and pre-requisite

ISTs remain under EN/ACE responsibility, and correspond to each line in the planning

Kept simple, equipment groups need to have the details. Intended only for tracking purposes, and should be completed by EN/ACE. Need to add David and Antonio to the list of checks (James).

All equipment owners contacted, and most of the tests filled in with 

David and Antonio will go through the IST planning, in a meeting which alternates with the SPS planning meeting. Were understanding that OP would fill this out? Kevin confirms that OP will take responsibility. 

Implementation of FFA in LSA (Kevin/Giulia)

Discussions held last week and agreed, now sent to Anthony. Don't yet all have the parameter names.

One question remaining on the one function needing calculation, virtual layer? Giulia says Up to OP, not much code to add, and rather simple.  

Arthur working on the beam control interface so can code this and in a few weeks can test this.

RF dry run outcome: generation 2 (Kevin)

Putting together full high-level-down-to-hardware RF parameter model

Testing now possible only on LSA PRO in VM, can't generate but essentially the same (some detailed differences).

Week 13 objectives defined building on the first test, details in the codimd tracking page 

Some of the items could not be tested yet, e.g. radial steering which needs the optics model and the FFA, plus some of the ATIMs (although concepts tested).

Note that if the voltage is trimmed the generation hierarchy is broken, but is now self-consistently treated (not in the past).

Need a default number from RF for the freeze RF, which can be trimmed after.

Stable phase function in LSA including raw value sent to HW, needed for the phase loop.

Tested as far as possible for LHC and SFTPRO beams. Results are correct.

Still need to sort out remaining issues and complete the tests, will need to be redone under real conditions in CCC when available, but will have debugged most things.

List of outstanding items shown, in progress.

For the calculation of the synchrotron frequency, depends on application, Kevin will sort out.

One question, when will this be released for others to use, e.g. dp/p for autoQ application? If there is a weely release then should be there, to test. Fabio will check. 

Is make rule for voltage function still compatible for LEIR? Yes, should be, to be checked if the approach is relevant.

AOB

Work on restart planning has started, depends on many factors including the contractors. 

Next meeting: 01/4/2020 (chair Kevin)