Notes from LIU-SPS update for ALPS
- Production status
- Tunnel and surface infrastructure complete including CIBUs (BA1, BA4 and BA6)
- 20 complete ‘pizza-boxes’ to be debugged / 10 needed for installation
- 10 ADC boards being produced – coordinated with MPE for production and assembly. Need to see with them when back at CERN
- Installation status including tunnel grounding (slide 5)
- Sextant 1: awaiting cables for grounding + coax cables right
- Sextant 2: awaiting coax cables left
- Sextant 3: to be disconnected for new lab test and reinstalled
- Sextant 4: awaiting fibres (right)
- Sextant 5: awaiting coax cables (right)
- Sextant 6 : finalised
- Proposal that Andrea/Thierry prepares table and sends to EN-ACE coordination
- Firmware status
- Final touches being put on firmware
- Interlock (hardware/software)
- List of channels for hardware interlock LSS4/LSS6 being prepared by Manoel and sent to Kevin et al for inclusion in the functional specification document.
- BI and OP software status (low-level and scripts/GUIs
- Non-linear position algorithm to be provided (Manfred)