CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
Presence at GIF needs to be limited to minimum. If you can work from remote - please do.
If your IMPACT has not been resumed - please do not come to the GIF.
(for exceptions, please contact Giuseppe or Martin)
----------------------------------
ATLAS-MM : SM1 long term chamber inside bunker. (2-3 months)
From next week very busy with several chambers arriving.
ATLAS - sTGC : test in the bunker on Friday and likely another on Monday. After that we will probably be quiet for a little while until new chambers arrive.
CMS-CSC: Resuming main work next week
EP-DT1: Standby
EP-DT2 : source off scans for EPDT2, everything was ok
CMS-DT: Expected to return to bunker around September.
EcoGas : some interventions were performed yesterday on the setup
CMS-RPC : Started. Needs to be flushed for some time due to long OFF.
HV scan with source off done, source on scan now planned.
Trolley 147914 goes out next week.
ATLAS-RPC: BIS78 transport approved. gas gaps to be tested in the next weeks.
ATLAS-sMDT (Gregor) : First visit to bunker, will come back with new plan
==========================================================
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1
-------------------------------------------------------------------------------------------------------
Auto-Transfer Test : 17.07.2020
Test Normal Secours 2020 : 30.7.2020
Current estimated NA beam start : 12/07/2021 (2.5 months delayed)
---------------------------------------------------------
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.
introduction, goal of the test, plan, needs
Bulgaria academy of science -> testing of new type of radiation monitor system
A new setup of ALICE-RPC will come. More news in coming weeks.
Lab on Fiber (LOF) dosimeter
Gas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).
Improvements needed or planned for the facility.