NSW Readiness Review - July 20, 2020
-
Will review whether NSW-A can be completed in time to be installed during this shutdown (requires a readiness date in Spring 2021)
-
Will also discuss the schedule for NSW-C
-
Most chambers for NSW-A have arrived at CERN and have been assembled (see table below)
-
Will mostly discuss the timeline of preparing the chambers for installation, and then commissioning (eg. services installations, electronics, gas-leak sealing, etc)
Status at CERN (as of 10-07-2020)
Detector type
|
Chamber type
|
Needed (A side)
|
Completed*
|
sTGC
|
small confirm
|
8
|
8
|
small pivot
|
8
|
7
|
large confirm
|
8
|
4
|
large pivot
|
8
|
7
|
MM
|
small A-IP
|
8
|
8
|
small A-HO
|
8
|
8
|
large A-IP
|
8
|
5
|
large A-HO
|
8
|
5
|
*Meaning they have arrived at CERN, been through GIF++, had alignment platforms installed, and been assembled into wedges. Does not include status of services, electronics, etc.