LIU-SPS Coordination Meeting
Zoom
LIU-SPS Machine Coordination Meeting 30/09/2020
Present: Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne.
Matters arising and actions
- Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. RF working on this, report expected for mid-September; Kevin suggested to discuss the operational handling of interlocks in August --> RF still preparing to finalize topic internally; will ask for reports in one month; then pick up on these. Kevin to remind RF.
- Open action: Jminuit not compatible with JDK11. Verena find other solution. Not before mid of October
- From AC coating, question of how to keep expertise through LS3
- Hysteresis modelling has first version ready for CCC needs some debugging of the python implementation, everything else ready.
- XTIM distrution is done.
- Open action: WS Spec still to release
- Done: Ivan and RF to check HW requirements for 800 MHz use to stabilize AWAKE beams.
- Open action: Verena to check (2021): QF 50 Hz correction for all cycles?
- Open action: David to add to list for YETS/LS coating of 414 and 616.
- Open action: Vacuum team: store some coating samples in vacuum for comparison and long term studies.
- Open action: Rende/Hannes/Verena: schedule high intensity scrubbing beginning of 2023 to define coating strategy for LS3
- Brennan has triggered discussion after feedback from LHC experiments: SPS ion commissioning versus LHC commissioning 2021. Still to arrange zoom meeting with RF and OP (Brennan)
- Open action: 20 minutes cool downtime after TIDVG intensity interlock. Francesco/EN-STI: Define options for start up.
- Open action: schedule ALPS dry run in 2 weeks (Kevin).
- Open action: Bren to check the ORA invitation list with Nasia.
News on dry-run and test progress
- ALPS dry run on 24/9 could not take place, but still drove some HW preparation and progress. Will take a week to sort it out, will try and reschedule next week. Multiturn was tested in 2 weeks.
- RF Functions FESA classes are coming in, and being finalised, will then upload and start with the full LSA parameter model. Beam Contol FESA class is also online and testing started with OP. Acquisition class also online and can start looking with the CCC Application. Cavity Control class still pending, being worked on by RF.
ALPS Dry Run (Verena)
- Tested new multiturn application, which is a generic application across the complex from the OP SW team.
- Checked out the basic functionality including acquisition and harmonic analysis
Beam Commissioning and Scrubbing, How to operate the SPS with new systems: Skeleton ORA (Kevin)
- Outline of the talk for the SPS ORA, breakdown on system integration and commissioning plans for RF, ALPS, SBDS.
- Include operational use cases, procedures, applications, diagnostics, specifics.
- Need to make sure minimum overlap with other talks, like on the dry runs and the upgrade scope.
Round Table
- OP will start weekly Monday morning 08:30 meetings to coordinate the SW deployment, Dry Runs and HWC, eventually turning into the Machine Coordinators meeting. Linked to this we would propose to more the short-term progress and planning (1-2 week horizon) into the Monday Coordination Meeting, and to eventually reduce the frequency of the Wednesday meeting to once per 2 weeks. Will start with OP and RF experts, then build up as we go on.
- ORA dates moved to 26 and 27th October, to allow the results of the RF MCM on 7/10 to be included.
- OP working with CO to look at speeding up deployment of Beam Performance Tracking plotting. Have a first version of the optics online.
- Working on uploading the TL optics, in progress.
- Discussion on long. emittance blow up have started.
- Still 2 vacuum sectors to close in LSS5, on track.
- Shutdown progressing, 2.5 weeks until IST period begins, some concern about a few last-minute items. Global cleaning is under way, some BAs done already, will finish in BA5, starting BB5 from 16th Nov - 27th Nov, with one week to make final cleaning.
- Information on ZS MS, OP should have the FESA classes in 2 weeks, should not have any changes to the interfaces.
- Discussed possible HiRadMat interlock to protect window and dump, in discussion.
- System to prevent extraction deadlock in LSS4, can apply to LSS6, needs some additional HW to make it in conformity. ABT checking if this is feasible.
- Possible to make AWAKE voltage and phase jump with 200 MHz but not with existing 800 MHz (would need HW upgrade). Has been checked by Ivan and this also gives good results.
- Small errors in the optics for FT in the Q', is the new version now working? Yes, confirmed OK by Stephane.
- For the logging making the requests for the FGCs, some concerns on the selector, looking for the issue with EPC and CO. Same issues with SIS for the FGC.
Agenda for next meeting (07/10/2020)
- Status of RF hardware installation and power commissioning E. Montesinos
- Status of RF LLRF hardware Philippe
- Status of RF CS Andy
- RF system integration status Kevin
- Overall RF commissioning milestones Frank