LIU-SPS Coordination Meeting

→ Europe/Zurich
Zoom

Zoom

https://cern.zoom.us/j/95974204283

LIU-SPS Machine Coordination Meeting 23/09/2020

Present: Andy Butterworth, Anthony Rey , Brennan Goddard,Chiara Pasquino, David Mcfarlane, Elena Chapochnikova, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti , Frank Gerigk, Giulia Papotti ,Hannes Bartosik , Ivan Karpov, James Ridewood ,Johan Dalla-Costa, Kevin Shing Bruce Li ,Lars Jensen, Luciana Kolbeck, Paul Cruikshank, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Verena Kain, Wolfgang Hofle, Wil Vollenberg 

Matters arising and actions

  • Done: Kevin to clarify availability of total voltage measurement from LLRF. Confirmed from PB that this will be available in digital and analogue
  • Done: Marine/Eric check with Greg whether also SIS logic provided; Eric waiting for reply from Greg --> check for end August; nothing critical, Greg is on vacation. Still no news. => SIS subscription is now ongoing; issue opened and on good track.
  • Open action: Kevin still to organise discussions between OP/RF to integrate RF power interlocking with BIS/SIS/SPSQC/Big Sister, other applications. RF working on this, report expected for mid-September; Kevin suggested to discuss the operational handling of interlocks in August --> RF still preparing to finalize topic internally; will ask for reports in one month; then pick up on these. Kevin to remind RF.
  • Open action: Jminuit not compatible with JDK11. Verena find other solution. Not before mid of October
  • Done: Wolfgang to clarify with the LLRF team whether all HW requirements are met for 800 MHz slip stacking and whether system is ready in time for tests in 2021 => 800 MHz requirements will be checked and discussed internally within RF in preparation for the SPS MCM early October.
  • Done: Verena/IPP ensure availability of CALS in read-only mode beyond LS2. => NXCALS will be followed up in an LMC and IPP; CO is aware of request to keep CALS readable for a longer time; potential loss of data.
  • Done: impact of installation of MKP-L and shorten run 2021. How much shutdown does the SPS need beyond EN/EL, BE/ICS and CV maintenance 2021/22.
  • Done: OP to check completeness of IST lists - Kevin/Verena/James/Stephane
  • Open action: Brennan to check HW delivery schedule with Erk, Frank and Co. --> Will come October 7
  • Open action: Verena & Co to organize meeting for SIS and XTIM distribution etc.
  • Open action: Verena to release WS EDMS doc.
  • Open action: Ivan and RF to check HW requirements for 800 MHz use to stabilize AWAKE beams.
  • Done: Chiara to check required ECR modification with Sonia.
  • Open action: Verena to check (2021): QF 50 Hz correction for all cycles? 
  • Open action: David to add to list for YETS/LS coating of 416 and 616. 
  • Open action: Vacuum team: store some coating samples in vacuum for comparison and long term studies. 
  • Open action: Rende/Hannes/Verena: schedule high intensity scrubbing beginning of 2023 to define coating strategy for LS3
  • Open action: Brennan trigger discussion after feedback from LHC experiments: SPS ion commissioning versus LHC commissioning 2021.
  • Open action: 20 minutes cool downtime after TIDVG intensity interlock. Francesco/EN-STI: Define options for start up.

ISTs on crab cavities are in the EN-ACE planning. Chiara agreed with Sonia that the ECRs will contain a modification to ensure that drawings are updated in case. In case more details then a check in a table are required, a dedicated document needs to be provided (e.g. SPS dog legs). 

News on dry-run and test progress

No news

a-C coating: LS2 report (Wil)

Wil summarised the very successful a-C coating campaign in the SPS during LS2. The whole activity was exemplary in terms of preparation, tooling, planning, execution and tracking. The SEY results from the samples are consistently below the required thresholds for the various chambers. Verena asked whether during the routine QF inspection as part of the quality check after coating, part of the coating is not damaged. Will mentioned that the endoscope is on special rails mounted on the side and the coating strips are on top and bottom of the chambers. Paul asked when there would be a slot to finish the coating of 414 and 616 which could not be done to avoid venting the MKEs. This will have to be added to the list, no date is defined for the time being. Elena asked what the error on the SEY measurement could be. Will mentioned that there could be a maximum shift of the value by 0.04. Brennan mentioned that one of the samples should be re-measured with all SEY measurement systems. All samples are transported and stored in air in Al foil. To draw conclusions on ageing, some of them should also be stored in vacuum. Elena also wanted to know about the impedance reduction campaign and whether any issues where encountered. Will mentioned that there will be a dedicated talk on this subject in one of the upcoming meetings.

a-C coating: extrapolation to LS3 (Paul)

Paul showed what needs to prepared to continue a-C coating during LS3, where QDs and MBBs need to be done. More equipment will be needed to fit into the LS3 time. Currently this activity is not in the manpower and budget planning. This would have to be added and can be cancelled afterwards in case, according to Brennan. The approval whether to go for coating in LS3 needs to come at the latest in 2023 to recruit teams and purchase equipment. Hannes confirmed that middle of 2023 we should have the answer according to the LIU parameter ramp-up. A high intensity scrubbing run would have to be scheduled explicitly. Brennan wanted to know whether we have to ensure not to lose the expertise and training to run the tools. Paul answered that due to the HL campaigns, some of these activities will continue. He also added that it is important to ensure correct storage of the equipment. Will said that in case of exchange of MBBs, coated ones should be installed. This also will keep a low grade coating activity going. 

Hysteresis modeling migration (Nico) 

Nico presented the first version of a tool that will predict hysteresis and finally correct for it based on neural nets trained on lab main quadrupole data by the magnet group. All the technicalities of triggering the predictions at the correct moment and picking up the currents from LSA have been sorted out. Unfortunately the python implementation of the NARX network as was used by the magnet team in matlab or the configuration as is used does not reproduce the results as expected from the machine (change of flattop field after super cycle change that stabilises after about 7 super cycles). Another discussion is organised with the magnet team to verify all the aspects of the usage of NARX in python. Maybe other network architectures will have to be tested. 

Round Table

Kevin mentioned the scheduling issue of ion commissioning in the SPS wrt to LHC RF commissioning in 2021. Reyes replied that this needs to become an LIU discussion and should not be decided in the BE department. Etienne reported that things are advancing well in LSS5 after an alignment issue was sorted out for UA9 equipment. Francesco told the meeting about the TIDVG intensity interlock to prevent deformation and impact on the aperture. The 20 minute cool down time that is requested after an interlock trigger, is not very comfortable for operation. For the startup the numbers as proposed will be used.  Stephane added that the survey team has communicated the proposed smooth line for the SPS ring. A few more quadrupoles were asked to be aligned along it, otherwise the alignment seems to be good. 

Agenda for next meeting (30/09/2020)

  • ALPS Dry Run Verena
  • BC and scrubbing: Kevin
  • How to operate the SPS with new systems: Skeleton ORA Kevin
There are minutes attached to this event. Show them.