EuCARD2 standalone integration meeting

Europe/Zurich
    • 15:00 16:00
      Discussion 1h
      Speakers: Dr Carlo Petrone (CERN), Franco Julio Mangiarotti (CERN), Helene Felice (Université Paris-Saclay (FR)), Luca Gentini (CERN), Maria Durante, Matthieu Canale (Universite de Savoie Mont-Blanc (FR)), Thibault LECREVISSE (CEA-Université Paris-Saclay (FR))
      • still need to decide which 2 coils (of the 3) to use
      • magnet is slightly longer than expected, probably too long for cryostat depth
        • possible solution: remove top plate of Eucard
      • joints between magnets already done
      • 2 meter HTS leads: try to reuse the same solution for HTS leads as in Feather
      • assembly schedule will make delivery very tight for testing magnet before end of year
        • no more delays possible if testing to be completed before end of year

      Nominal testing schedule, EuCARD2 & Feather2: not exactly in parallel because using same power converter, but we want to do in parallel as possible. Probably mount Feather in Fresca before EuCARD2 arrives, but EuCARD2 may arrive before Feather is done (assuming no delays)

      Maria will send Daniel best estimate for actual delivery date to CERN and decision will be made whether testing can be done before end of year.