LIU-SPS Coordination Meeting
Zoom
LIU-SPS Machine Coordination Meeting 14/10/2020
Invited: Andy Butterworth, Anthony Rey , Brennan Goddard,Chiara Pasquino, David Mcfarlane, Elena Chapochnikova, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti , Frank Gerigk, Giulia Papotti ,Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Jaime Espinos, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Stephane Cettour Cave, Verena Kain, Wolfgang Hofle, Yannick Le Borgne.
Matters arising and actions
- Power interlocking; being followed up - now need to get together with OP to look at impacts
- JMinuit still open
- WS specs not yet released
- 50 Hz correction longer term - can be looked at ni 2021; needs new electronics
- Done: Coating 416 and 616 is added
- VSC storage of samples not yet followed up; to be checked with team
- High intensity scrubbing coating strategy for LS3; still open and needs to be folded into the schedule for 2023
- Done: Ions and LHC commissioning not compatible; current baseline is the SPS ion commissioniong
- TIDVG interlocking still being looked at - trying to reduce the 20 minutes waiting time;
- Done: ALPS is scheduled, invitations sent around, SPS island is reserved
- Done: ORA invitation list has been updated
News on dry-run and test progress
Discussion took place during Monday 8:30 meeting
Impedance reduction outcome and lessons learned (Jaime Espinos)
Jaime reported on the impedance reduction campaign at QF SSS as well as QC and consolidation in case at the QD aperture repair locations during LS2. The planning for the installation was established together with aC coating campaign. Dashboard was very useful efficient communication of status of activities across multiples teams (e.g. VAC, RF,...). Tooling, workflow etc was already tested before (staged deployment). 246 new shields and/or fillers installed, 92 shields and/or fillers installed linked to existing design, 218 existing shields inspected and fixed where necessary. Installation was followed by RF and dimensional measurements for QC. Due to bellow over-extension a few NC were identified that could have impact on long. impedance (locations: 33010, 51210, 62010). Tracking: all shields, fillers and stop ends coded and tracked. Will go into layout DB. Stock of spares consolidated. Overall very well prepared and well organised campaign, profiting from staged deployment (tests during YETS before), collaboration, communication and work procedures, QA and tracking.
UCAP server deployment and workflow: and SBDS example (Francesco Velotti)
Francesco showed his progress on combining various technology to provide an XPOC like system for the SPS beam dump. Analysis is based on the BTV image with a variational autoencoder to define the parameters such as bunch pattern, numbers of pulsing MKDs etc. Based on this the nominal pattern will be defined and compared with simulation data. All this will be running on UCAP, results will be published to logging and be picked up also by the SPSQC. Another ML analysis that will be running on this UCAP node will be the field prediction of the measured current in the kickers. Francesco also provided detailed notes - an almost tutorial like description - of how to set up UCAP for such purposes.
AOB
No AOB
Agenda for next meeting (4/11/2020)
to be defined