PS BGI systems (James/Steen)
- Mechanics/detectors
- BGI vertical magnet and vacuum chamber installed in August
- BGI horizontal upgraded version being prepared
- Ceramic PCB assembly proved difficult (soldering)
- Timepix modules being assembled with EP-DT wire-bonding lab
- In-vacuum instrument installation (scheduled for W1/2021)
- Measurement modes (EDMS document: 2397728)
- Beam profile (OP), Raw-data (MD) and TV (live view)
- Electronics:
- Reminder of system blocks from tunnel to surface (building 355)
- Back-end will be based on VFC with HDMI mezzanine (BI built) once the system is commissioned (during 2021) - should be transparent for FESA software
- Firmware (Hampus)
- APIs documented on EDMS document : 2407507)
- Software (Steen)
- Request to acquire 100 profiles per cycle (operational settings)
- BGIPXL FESA server accesses other devices (LTIMs and slow control)
- Main communication from FEC to firmware based on IP-BUS (BE/CO now supports library and utility)
- Possible topic for a future TB meeting
- Description of the expert and operational properties and property to debug RT actions
- BI expert application based on Python
- BI-TB presentation proposed Spring 2021
- First version of FESA server released
- Operational integration for profiles by M. Cody (BE/OP)
SPS BGI systems (James)
- Current system status:
- Vertical device moved during LS2 (beam dump project)
- Instrument installation was foreseen next week
- 15kV electrical feedthrough issue found on H and V
- Inner connector diameter does not fit the HV cable plug (inner diameter too small)
- Solutions under consideration with ML section (await installation until early 2021?)
- BGI imaging systems appear to be available (two intensified cameras are working)
- MCP ageing not seen as primary problem (operational use to be clarified)
- Federico asked to present SPS BWS, BGI and BSRT performance by early 2021
- Consolidated system (LS3)
- Various components show weaknesses
- New SPS BGI based on PS system
- Main difference is distance from cathode to anode, the rest should stay as PS
- Tentative (realistic?) plan shows we could have instruments ready by 22/23 YETS
-