Adhoc BI-TB for PS/SPS BGI systems

→ Europe/Zurich
CERN

CERN

Description

https://cern.zoom.us/j/95505784430?pwd=UWswZ2hvRGlRc3NnTmxYTTBGRDZkQT09

PS BGI systems (James/Steen)

  • Mechanics/detectors
    • BGI vertical magnet and vacuum chamber installed in August
    • BGI horizontal upgraded version being prepared
    • Ceramic PCB assembly proved difficult (soldering)
    • Timepix modules being assembled with EP-DT wire-bonding lab
    • In-vacuum instrument installation (scheduled for W1/2021)
  • Measurement modes (EDMS document: 2397728)
    • Beam profile (OP), Raw-data (MD) and TV (live view)
  • Electronics:
    • Reminder of system blocks from tunnel to surface (building 355)
    • Back-end will be based on VFC with HDMI mezzanine (BI built) once the system is commissioned (during 2021) - should be transparent for FESA software
  • Firmware (Hampus)
    • APIs documented on EDMS document : 2407507)
  • Software (Steen)
    • Request to acquire 100 profiles per cycle (operational settings)
    • BGIPXL FESA server accesses other devices (LTIMs and slow control)
    • Main communication from FEC to firmware based on IP-BUS (BE/CO now supports library and utility)
      • Possible topic for a future TB meeting
    • Description of the expert and operational properties and property to debug RT actions
    • BI expert application based on Python
      • BI-TB presentation proposed Spring 2021
    • First version of FESA server released
      • Operational integration for profiles by M. Cody (BE/OP)

SPS BGI systems (James)

  • Current system status:
    • Vertical device moved during LS2 (beam dump project)
    • Instrument installation was foreseen next week
    • 15kV electrical feedthrough issue found on H and V
      • Inner connector diameter does not fit the HV cable plug (inner diameter too small)
    • Solutions under consideration with ML section (await installation until early 2021?)
    • BGI imaging systems appear to be available (two intensified cameras are working)
    • MCP ageing not seen as primary problem (operational use to be clarified)
    • Federico asked to present SPS BWS, BGI and BSRT performance by early 2021
  • Consolidated system (LS3)
    • Various components show weaknesses
    • New SPS BGI based on PS system
    • Main difference is distance from cathode to anode, the rest should stay as PS
    • Tentative (realistic?) plan shows we could have instruments ready by 22/23 YETS
    •  