LIU-SPS Machine Coordination Meeting 11/11/2020

Invited (from): Alexander Huschauer, Andy Butterworth, Anne Funken, Anthony Rey ,Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard,Chiara Pasquino, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Eric Veyrunes, Etienne Carlier ,Fabio Follin ,Francesco Maria Velotti ,François-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti ,Gregoire Hagmann ,Grzegorz Kruk, Hannes Bartosik , Ivan Karpov, Ivan Romera Ramirez, James Ridewood ,Johan Dalla-Costa, Jonathan Meignan, Julie Coupard, Kevin Shing Bruce Li ,Lars Jensen, Loic De Oliveira, Louis Pereira, Luciana Kolbeck, Malika Meddahi, Marine Gourber-Pace, Mauro Taborelli, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Sonia Bartolome Jimenez, Stephane Cettour Cave, Sylvie Prodon, Verena Kain, Wolfgang Hofle, Yannick Le Borgne, Tomasz Ladzinski

Matters arising and actions 

  • Federico will come to explain about WS/BSRT/BGI protection, will be in January (including ions). What to expect from our emittance measurement systems?
  • Dynamic injection pattern to synchronise with timing system and BQM, being followed-up.
  • Power interlocking clarified for Thales; how to include Siemens and Philips?
  • JMinuit upgrade to other library
  • 50 Hz correction longer term on all cycles- can be looked at during 2021; needs new electronics
  • VSC storage of some samples under vacuum not yet followed up; to be checked with team
  • High intensity scrubbing coating strategy for LS3; still open and needs to be folded into the schedule for 2023
  • TIDVG interlocking still being looked at - trying to reduce the 20 minutes waiting time;

News on dry-run, test progress and LS2

  • Dry run on RF frequency program from B-train, still issue with RF function generator firmware, but could still usefully test some other parts. Could send scalers and check the whole chain. Try to retest asap when fix done.
  • Also would like to test transactional behaviour for RF, next week.
  • With ALPS trying to have stable FEs for the different CCC applications, end of this month.
  • LSS5: Second wire scanner being installed. BGI not ready for installation. BI already in contact with HWC coordination to define slot during HWC. Should be OK. 

Proposal for updated ion commissioning plan (Reyes) 

  • Plan does not include FT ion cycle (as per present assumption for 2021)
  • Need dry-runs and HWC all finished
  • Plan tuned in view of 2021 time available.
  • Includes other steps needed, not just for LL RF  (like BI, ADT)
  • Propose 2 cycles - "short" (2 injections) and "full (14 injections)".
  • Cycle decomposed with synchro, radial loop and FFA
  • Tentative plan should fit into 2 weeks, after the LHC beam test, with the top priority, and is:
    • 2 days at flat-bottom with short cycle
    • 1 day for FFA and ramp to 300 GeV
    • 4 days for 800 MHz commissioning at 300 GeV and blowup (if needed)
    • 5 days for slip-stacking and radial to synchro loop switch
    • 2 days for ramp to 450 GeV
  • Aim is to have machine for OP for the weekends to be cleaning up ramp etc. Modular enough to be flexible for this.
  • Second period is with long flat bottom, same steps but repeated with increasing numbers of batches, and (maybe) transverse damper commissioning
  • 2 days planned for this, to show that there are no fundamental problems. 
  • Can't have both long and short ion cycle in the SC, as too long, OP will look at longer term removal of this limit (SPS-OP)
  • Need to get the commitment from RF LL about the readiness for this (HWC and dry-runs).
  • There are some other aspects to be included, like 800 MHz to be commissioned from below transition (but can't run 800 MHz with FFA). Giulia to send these considerations to Reyes for the discussion with Philippe.
  • Also proposal to test with protons the 800 MHz on through transition, to also check (Reyes).
  • Objective should be clear, to demonstrate slip-stacking mechanics and technicalities and check for unexpected problems, not the fine-tuning for optimum performance.

Access system tests outcomes (Tomasz)

  • 16 access points installed and in operation (one in restricted mode)
  • 12/16 access zones (sites) installed
  • Focus of week 45 for testing ring, TI2, TI8, interlock chain, EIS, CCC. Missing NA as late.
  • Long sequence of tests including AWAKE for e- and laser, as well as patrols and extractions and TLs.
  • All critical corrections have been implemented
  • Various feedback from OP: still some causes for losing patrol, including doors, PADs, MADs. Some TIM views to improve. Special features are helpful.
  • EiS from 18 kV could not be tested yet. Will see during DSO test.
  • Need additional 3 days during HWC in March for access system finalisation of NA and AWAKE proton mode.
  • Overall access system installation on time and tests successful. Ready for HWC.

AOB:

  • Update on TIDVG interlocking (Francesco)
    • Update of current interlock: limit protons/s stays the same. Cool down time will be set to 5 minutes.
  • Update on RF interlocking (Andy)
    • Interface, diagnostics, redundancies (running with 1 line off clarified). Strategy looks for the Thales plants. FESA class for diagnostics and control (e.g. unlatch) will come in January. 
    • The proposal allows for auto-masking. SIS will ensure not running the SPS for high intensity beams in case the required power cannot be guaranteed (state check of various lines). 
    • Siemens and Philips plants will not have a fast interlock a la Thales.

Agenda for next meeting (18/11/2020)

 