    • 11:00 → 11:05
      New Announcements 5m

      IMPACT Declarations 2021 : 

      For 2021, please prepare a new request, with "GIF - Irradiation 2021" as intervention period.
      If you clone the one from 2020, please review the description and the participant list !

      You will need an active IMPACT to activate the DCM and enter the bunker.
      List of active IMPACTS : PPE154

      Please update the label on your setup. (Needs to start with 16xx)
      ----------------------------------

      Annual User Meeting 2020 : 

      DATE : TUESDAY 26.01.2021
      We expect a report of your ongoing measurements, and outlook on what is needed during the rest or LS2 and  your plans for your 2021 beam requirements.
      Agenda currently finalised at.... : https://indico.cern.ch/e/GIF-AUM-2020
      ----------------------------------

      CALL for Muon Beam Time  : 
      See dedicated agenda point.
      ----------------------------------

      F-Gas Inventory - EP : 

      Usage at large experiments known.
      In case you use F-gas in your lab for small setups or R&D - please contact Roberto Guida !!

      ----------------------------------

      Access System Maintenance  :

      Two days of Access System unavailable.
      Proposed : Tue & Wed.
      Second half of February.

      ----------------------------------

    • 11:05 → 11:15
      Muon Beam Request 2021 10m

      North Area Physics : 12.July to 14.November 2021
      All requests for Muon beam time at the GIF++ facility have to be send to  
      GIFPhysics.Coordinator@cern.ch 
      (Martin)
      Deadline : FRIDAY 22.01 !!

      So far received :

      • EP-DT2        (3x2 weeks)
      • CMS-DT      (2x2 weeks)
      • RHUM         (1x2 weeks)
      • CMS-RPC    (2x2 weeks)
      • iRPC             (2x2 weeks)
      • NSW-MM    (18 days)

       

    • 11:15 → 11:30
      Weekly planning 15m

      WILL BE UPDATED DURING THE MEETING !!!

      ----------------------------------

      Weekly Planning :   https://teamup.com/ksvh7dak8mub8k7xpe 
      UPSTREAM :          Default filter settings :  2.2 
      DOWNSTREAM :   Default filter settings :  1

      ----------------------------------

      ATLAS - MM :
      SM1-M31 long term chamber inside bunker since August. IC4H10 test ongoing.
      SA - access request for gas swapping (Ar-Co2) before removing chamber.
      3 long term chambers placed (on the ceiling) + 1 quad will be installed today THU 10th and swapped with the one that is currently inside.

      ATLAS - sTGC :  New chambers arrived, under test. New stand for flushing chambers before testing. Chambers arriving from Chile, not yet shipped. Some problems to solve with one chamber due to high impedance.

      ATLAS - sMDT :  Some noise problem currently under investigation (getting better). Gas quality will be changed from class II to class III (bottles ordered and expected next week)
      REQUEST : 2-3 days at the end of next week running with max filter in upstream (outside sTGC tests)

      CMS - CSC:  Progressing with the activity to resume everything after the long stop.

      EP-DT2 :  System restarted. The aging test with eco-friendly gas mixture are going well. 

      CMS-DT:  Expected to return to bunker later / next year. INFN still blocking activity outside Italy. Preparing for the shutdown and most probably switch to low gas flow already today or tomorrow. 

      EcoGas:  New detector installed. Restarted. Test campaign resumed using standard mixture (R134a, iso-butane, and SF6).

      CMS-RPC: Radiation program resumed on trolley 1. Some impedance problem to solve on the new chambers. Gas kill signal that didn't work when the R134a- FIXED. Proposal to keep 4.6 as default attenuation filter for one week - outside sTGC measurements.

      ATLAS-RPC: Coming back for the moment, not before March 2021.                       

       
       
       
       
       
       
       
       
       
       
       
       
    • 11:30 → 11:35
      New requests for tests at GIF 5m

      introduction, goal of the test, plan, needs

      BLM measuring campaign announced / ≈ 100 BLM, 6h approx. Week 45 (November 2nd till Friday 6th ). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup    -> postponed until next year

      ----------------------------------

      Bulgaria academy of science -> testing of new type of radiation monitor system

      A new setup of ALICE-RPC will come. More news in coming weeks.

      Lab on Fiber (LOF) dosimeter

      Gas recuperation system to be installed - Responsible : Roberto
      4 additional racks in Gas Service area. One containing flammable gas.
      FG detection system to be installed, power needs to be provided.
      (DELAYED by a few months. Will be first installed in CMS, and only later come to GIF)

    • 11:35 → 11:40
      Long Term Planning 5m

      Gas usage at GIF :  we need to compile a table of gas mixture / consumption

      Gas training courses : ATEX level 1  and F-Gas training courses.
      List of trained people to be collected.

      Start to check the position of the CMS-DT chamber for the debugging. It would be nice if we can put it, either in the prep. area or beside the fence (near the XTDV motors) 

       
    • 11:40 → 11:45
      Infrastructure & Upgrades to the Facility 5m

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)

      - Upcoming intervention on Access System : controller upgrade. 2 days of work.
        Will be organised around a Wednesday (e.g. Tue. & Wed) in the second half of February

       

      - R134a supply system went off yesterday Wednesday DEC 02nd around midday. It seems that the issue is the main pressure regulator from the building 909 (picture attached). The same problem happened again on Thursday DEC 03rd. EN responsible are aware and an action will be taken by the end of the day. On January 6th-7th 2021 we had again a similar problem with the R134a.                                                                                                                     After all this issues, the system has been modified and a new panel with a new pressure regulator has been installed (13 Jan 2021), waiting for the overall renewal of the area 909. For the moment, the system it seems to work fine. In any case, we will monitor over the next weeks the status of the R134a line. 

      - yesterday Wednesday 20.01 our AULs system has been by-passed in order to start the removal of an old electrical switchboard a bit upstream of the GIF++ control room. During this intervention, the AUL line wasn't triggered.       Next Wednesday 27.01, after the removal of the switchboard and in order to put back our AULs system to standard condition, there is again a small (but not zero) risk that the AUL line will be triggered and we could have a short power-cut. As EN/EL is on site for this, we expect that any power-cut that happens is just a few minutes.           The proposed start date is  27.01.2021 at 9h. So, this is during our normal access day.

       

       

       

       
       
       
       
       
       
    • 11:45 → 11:50
      General Items 5m
      • IMPACTs for 2021 5m

        Guidelines for filling in IMPACT requests

        List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154

        General Guideline : One IMPACT per setup.

        • two chambers on individual supports -> 2 IMPACT declarations
        • multiple chambers swapped on same or similar support -> one IMPACT declaration
        • basically, if you need two locations, please make two IMPACT declaration (clone)

        Each Setup should have IMPACT label attached with number.
        Attached documents : CAD file  or  picture.
        Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes).

      • CoVid-19 5m

        CoVid-19 Risk Assessment for the Facility :  https://edms.cern.ch/document/2376286/1

        General guideline :

        • ONE setup to enter the bunker at any given time.
        • All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
        • Traceability of people on site :  Logbook ! - List all the people you encountered.
    • 11:55 → 12:10
      AOB 15m

      No AOB this week