LIU-SPS Coordination Meeting
Zoom
Present: Alexandre Lasheen, Andy Butterworth, Anthony Rey, Antonio Grande Mallavia, Arthur Spierer, Brennan Goddard, Carlo Zannini, Chiara Pasquino, Christine Vollinger, Christos Zamantzas, Danilo Quartullo, David Mcfarlane, David Nisbet, Elena Chapochnikova, Eric Montesinos, Kiki Veyrunes, Etienne Carlier, Fabio Follin, Francesco Maria Velotti, Francois-Xavier Nuiry, Frank Gerigk, Gerd Kotzian, Giovanni Rumolo, Giulia Papotti, Gregoire Hagmann, Hannes Bartosik, Heiko Damerau, Ivan Karpov, Ivan Romera Ramirez , James Ridewood, Johan Dalla-Costa, Johannes Bernhard, Julie Coupard, Kevin Shing Bruce Li, Leandro Intelisano, Loic De Oliveira, Luciana Kolbeck, Maciej Suminski, Marine Gourber-Pace, Michael Schenk, Nico Madysa, Nicolas Magnin, Paul Cruikshank, Philippe Baudrenghien, Reyes Alemany Fernandez, Simon Albright, Stephane Cettour Cave, Tom Levens, Verena Kain, Wolfgang Hofle, Yannick Le Borgne, Zisou Charilaos
Matters arising and actions
- ACTION - A. Butterworth: provide update on interlock interfaces along with available diagnostics (interlock tree - what triggered the dump?) ;
- ACTION - P. Baudrenghien: update simulation results with input parameters from operational scenarios, i.e., injected beam will be 2.6e11, 2.4e11 towards end of ramp; calculation for power with 10 kW outside beam segments; new algorithms for power optimization;
- ACTION - Kevin, Reyes, Giulia and Theo: look at parameter model of slip stacking to be implemented in LSA (e.g. duplicate RF voltage parameter);
- ACTION - Mike: keep following up on MKP potential vacuum issue with serigraphy upgrade;
- ACTION - Verena, Johan, Kevin: logging for TT10 power converters;
- ACTION - Ivan, Danilo, Giulia: get back to OP as soon as they can provide input in updating the LSA parameter model for longitudinal blow-up
- ACTION - Kevin: reach out to WS team for input on beam commissioning planning
- ACTION - SPS coordination: update AWAKE and HiRadMat pre-testing with latest RF schedule asap
Overview of beam commissioning plan: first week - Kevin
Kevin presented the first beam commissioning week with the updated input from RF. First beam 12th of April, for one day only, then switch back to RF HWC. Beam back then for Thursday after TS. Cavity control and WR2RF needs to be finalised. Hannes asked why nothing can be done in parallel to RF commissioning. Philippe replied that at this stage it cannot be guaranteed that all required manipulations are ppm. Tuesday 13th of April will be used for coordination of the rest of the week. Etienne added that Marco would like to re-discuss the commissioning of the TIDVG with beam. Brennan would like to know which form of coordination meeting will be carried out from Monday. Kevin mentioned that we will continue with the zoom 8:30 meetings.
Optimizers in preparation of commmissioning (ZS alignment, transition crossing) - Nico
Nico introduced the OpenAi Gym environments available for ZS alignment and tune function optimisation. Simulated as well as real environments are available. The ZS alignment was tested with real hardware, the SPSQC, but simulated losses following the typical response as measured in the past. With the BOBYQA algorithm alignment was achieved in promising 26 iterations.
Status hysteresis prediction and follow-up - Francesco
Francesco showed the latest break-through with the hysteresis modelling of the main quads in the SPS. By using physics inspired LSTMs that extended the loss function taking into account the dynamics with hysteresis he managed to provide networks that can be used to predict the fields for the next cycle. This approach shows hysteresis very well after a super cycle change for the SFT cycle at flattop. Nico provided the first full implementation to be used in the control room. For the time being it only predicts fields. For the next release the field changes will be translated into tune changes.