WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

Europe/Zurich
zoom (CERN)

zoom

CERN

URGENT ACTIONS: 

  • TCC test to be re-launch in automatic with good values of flow and outlet temperature
  • Emilien will bring the tank covers next time (TCLPX bending slot).
  • Luca will send the RF components to re-machine due to the new design, RF collar in priority
  • Inermet validation phase ongoing – 11th of April 
  • Shafts relative position in metrology -> find is the mistake in the assembly come from the tank, the jaws, the mechanical tables or the machining tools
  • RF screen to be disassembled
  • New TCLPX bending of the circuit to insert properly in the tank 

 

OTHER ACTIONS:

TCC:

  • Official cycles to be performed once the TCLPX will be available
  • Some data shall be clarified between Dylan and JMQ.
  • JMQ will test automatic cycles.

 

BPM flanges:

  • 4 new flanges under production to re-launch test
  • 1 test flange to try passive cooling

 

RF fingers:

  • Cycling ongoing without annealing and with 5um silver coting. Annealing for the next fingers.
  • Waiting for C1 on RF components 
  • We can assemble the RF component after tank closing if necessary 

 

Design 

  • TCLP, TCSPM, TCTPM folders: not started. 
  • Post-proto modifications regarding Dylan’s Excel: ongoing for jaws, done for mechanical table, almost finished for feet
  • TCTPXV review and modifications for serie: Emanuel working on it 
  • Mechanical table procedure check: ongoing 
  • Gabarit for cooling pipes production and assembly: ongoing
  • TCLM masks 
  • Copper wedges for jaws posing during vacuum test (STI)

 

Assembly:

  • TCTPXH to be inserted without blocks 
  • Tank Screen rails to be disassembled
  • TCLPX to re-bend  

 

Procurement:

  • Inermet blocks arrived at CERN, under validation
  • Nanoker will re-machine the wrong blocks 

 

Production MME: 

  • Tank cover arriving mid-March (input from Emilien) then cleaning.
  • Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118
  • BPM leaking flanges to solve with passive cooling. 
  • RF fingers 

 

Update on planning: 

  • Collimators shall be operational for July. 
    • RF fingers, Inermet, BPM flanges, and RF components 

 

Update for the serie:

  • LHCTC__X_T0001 aligner la surface de posage pour tournage coaxialite et tolerance sur piece T0006
  • LHCTC__X_T0002 triple contact a enlever car hyperstatique, risque de mauvais emmanchement pour soudage. + axe pas centrer sur le dessin.