FCC-ee tuning WG meeting
R. Tomas reports on the status of the FCC-ee tuning paper for IPAC'23. Magnet tolerances presented in the last meeting from E. Ahmadi are considered too ambitious by the magnet team and future studies including SR and tapering will be performed with the aim to ease them. One of the main challenges for optics is the predicted arc quadrupole magnetic axes shift by up to 0.1 mm when trimming
the strength of the two apertures independently. K. Oide comments concerning tuning studies performed by S. Liuzzo that the tune values should be mentioned. Furthermore, tolerances for coupling could be considered being included.
E. Musa reports on updates using LOCO in pyAT for orbit and optics corrections for FCC-ee relaxed ttbar-lattice without synchrotron radiation. Misalignments and field errors, presented earlier by T. Charles, are applied. For example with 10 µm arc quadrupole and sextupole offsets the sextupoles can be powered to their nominal value and 20 µm still allows for 99% of the nominal sextupole powering. This is the limit for successfully performed orbit corrections. R. Tomas comments that powering sextupoles to 50% of their nominal value seems feasible, which allows up to 40 µm misalignment tolerances. I. Agapov reminds that above 20 µm some simulations do not converge which is presently investigated. K. Oide comments that the response matrix calculation should include dispersion.
B. Dalena reports on orbit corrections for the booster ring. The goal is to define alignment and field tolerances for the dipoles, quadrupoles, sextupoles, orbit correctors and BPMs. Next to focusing quadrupoles horizontal BPMs and orbit correctors are included and vice-versa for the defocusing quadrupole. Beam threading is simulated a segment-by-segment technique for each arc one after the other. Afterwards orbit correction using 1 iteration with SVD is performed for the whole ring. No significant difference on the orbit between 10 and 1 units of field errors in the dipoles is found. First specifications of the main magnets misalignment of the High Energy Booster arcs cells show ~150 μm, corrected with orbit correctors with ~ 20 mTm. Tune matching does not converge for 30% of studied cases and SVD is not converging for BPM resolution above 50 µm. R. Tomas comments that beam based alignment could be envisaged also for the FCC-ee booster. K. Oide asks which field errors are expected at injection and during the ramp and their reproducibility. B. Dalena agrees to investigate these questions. The time for the ramp is presumed to be 1s, and damping time at injection is 10s, while about 3ms at booster top energy for Z-mode. R. Tomas advises to study emittance damping during the ramp with errors carefully to ensure reaching the design value.