PS/SPS User Meeting

Europe/Zurich
874/1-011 (CERN)

874/1-011

CERN

75
Show room on map
Eva Barbara Holzer (CERN)
Zoom Meeting ID
62626707960
Host
Eva Barbara Holzer
Useful links
Join via phone
Zoom URL

Minutes of the PS-SPS Users Meeting for Week 29 held on July 20th, 2023

The agenda for this meeting is based upon user schedule v1.6.0, please cf. here. Please note the current injector schedule which contains information about MDs, Technical stops, etc. and can be found here.

Next user meeting:
For week 30 on Thursday, July 27th, 2023 10:30 CEST
Meeting room 874/1-011

News from the PS & SPS Physics Coordinator (E. B. Holzer)

new user schedule online version 1.6 (counted that this is the 21st numbered user schedule since February)

See this codimd location from Tuesday morning onwards for the News from the FOM (E. B. Holzer)

Preview of MDs:

Week 29:

  • possibly a long parallel MD on Thursday 20/07/2023

Weeks 30, 31 & 32:

  • Dedicated SPS MDs for North Area with extraction to primary targets (T2, T4 and T6) and P42/T10 (up to TCC8)
  • Potentially last crab cavity test from 08:00-10:00 on Wed July 26 (week 30). If confirmed, no beam to North Area until 10:00 (sharp).

Intensity split

  • Until Thursday 20/07/2023: continue with SPS T2/T4/T6 = 30/72/45
  • From Thursday 20/07/2023 until Monday 31/07/2023:

T2 = 30
T4 = 100-110 / T10 <= 60
T6 = 45

PS Machine Report (Alex Huschauer)

Hardware issues:

  • Calibration of the position of the electrostatic septum SEH23’s actuation system -> EAST beam loss back to normal
  • Water leak identified on internal dump TDI48
  • Barrier bucket position jitters on SFTPRO resolved on Monday
    • no impact on performance for experiments, but slightly ?increased PS extraction losses
  • KFA13 required piquet intervention yesterday evening (2h without beam for SFTPRO)

Beams:

  • HRMT: plenty of super cycle changes and longitudinal splitting adjustments
    • EAST flux suffered from time to time, priorities rescheduled after discussion with Barbara
  • Prepared and sent TOF at 100E10 p to the target yesterday evening
  • SFTPRO intensity increase yesterday early afternoon
  • T9/TN target asymmetry plot available in CCC

SPS Machine Report (Arthur Spierer)

  • Availability from Thu to Thu: Overall 89%, NA: 89%, HiRadMat: 97.4%
    • Beam stop on Wednesday from 8:00 to 10:00 for CV and RF interventions
  • SFTPRO
    • Requested units starting from Wednesday on T2/T4/T6 : 30/105/45
    • Adjustment done
  • HiRadMat
    • Smooth run, high intensity extractions on Friday
  • No LHC beams since Monday
  • Parallel MDs on Monday, Tuesday and Thursday (replacement for previous week)
  • Next week
    • Short parallel MDs Monday and Tuesday
    • Dedicated on Wednesday
    • Parallel on Thursday
    • Empty bucket Channelling to be put in operation if experts available
    • Crab cavity MD Wednesday form 8:00 to 10:00 to be confirmed

Safety / Radiation Protection (Laura Rowland

  • Experimental areas and their control rooms are RP Controlled Areas - Please no food (or storing of food) in these areas.
  • Online ISIEC forms allow the granting of a three week safety clearance. If you plan to stay longer / extend your beamtime / make any modifications to your setup please contact the EP Safety Office to amend your clearance.

n_TOF (Nikolas Patronis)

EAR1: The second part of 243Am(n,f) measurement which is focusing on the higher neutron energies is going to start. For this measurement the 28ns longitudinal width is important to be preserved. 1 month long measurement. Today we have still to work on the setup for this measurement (beam-line modifications, supports, electronics optimization)

EAR2: 30Si(n,g) measurement is ending successfully. 64Ni(n,g) is about to start. This measurement will stay three weeks.

NEAR: In the activation area (a-NEAR) the repair of the moving table was successfully accomplished yesterday. Next week the diamond detector will be mounted as to test different electronics configuration. Irradiation hardness material studies are on-going in i-NEAR.

PoT: 1.10E19; Better than expected! Many thanks to the PS teams!

East Area Beam Status (M. Van Dijk)

T09: Continuing with low momentum configuration. No issues.
T10: Good operation. Yesterday installation of helium for low-pressure XCET for BL4S, to be tested today.
T11: No user just now.

East Area Users Tour de Table

T8: IRRAD / CHARM (F. Ravotti)

Good week, no issue with operation. Cumulative intensity delivered to T8 better than previous week (approching ~2E16 p/w, see plot below). Beam alignment on both X- and Y-axis OK (again >90% for X-axis) but less good that beginning of the year (~98% until week 22) - beam center has the tendency to slowly drift on X direction (see plot below where the red curve show the beam center intensity).

During the access on Wednesday, we exchanged dosimetry samples and all long-term users continue EP-ESE, TE-MSC [including N2 experiment], CMS Pixel [scanning table], RD50, etc. Installed 2 ATLAS experiments for HGTD and ITk Pixel [scanning table] (IRRAD). CMS DT and BE-CEM continue testing, ATLAS (DCT card) completed (CHARM).

Upcoming access, next week.

T9: WCTE (Akira Konaka)

Smooth data taking and some online results shows good pions to muon separation in the sub-GeV range. We will continue taking comprehensive data to study particle identification and each particle flux in sub-GeV range.
The magnet was finally shipped last Friday and will arrive in Geneva tonight. We develop a plan to install the magnet on Wednesday next week for the tagged photon beam study.

T10 Outgoing Main: ALICE ITS3 (Paolo Martinengo)

Smooth data taking, thank you very much for the 3 spills during the last evening/night, they were instrumental to complete measurement

T10 Outgoing Parallel: ALICE TIMING (Please Add Your Name Here)

T10 Main: BL4S (Margherita Boselli, Sarah Zoechling)

Experiment set up yesterday (scheme presented last week).
Many thanks to Abou and his colleagues, to the gas team, and to Inaki and his BI colleagues for their help!
Safety check took place this morning.
Beam hopefully today.
Aim is to calibrate the detectors, align the set up, and take some preliminary data.

T10 Incoming: RE21 CBM - Week 30 (Please Add Your Name Here)


Outgoing: HiRadMat (P. Simon)

MD + small experiment week.
Experimental program 95% done, waiting for wirescanner MD in SPS to extract higher intensities on Friday. MD on transferline optics and BTVs.

North Area Beam Status

H2, H4, H6, and H8 Beams (M. Van Dijk)

H2: Fault in trim that was resolved.
H4/H6/H8: Normal operation.

Other Beams P42, K12, and M2 (M. Van Dijk)

M2: First checks of the beam done with NA64mu. Three upstream profile monitors do not work. Local electronics to be replaced. Access is being planned.
P42/K12: All prepared for going to the NA62 beam dump run that will start today at 12:00. Yesterday after the intensity increase and going to the 40 mm long target at T4, we checked the correct transmission towards T10, aiming at running at about 55 - 57 units for the next 10 days. For last night, intensity on T10 was decreased by closing the P42 TAX to avoid too many changes in the machines and to the other users in H6 and H8.

North Area Users Tour de Table

P42-K12 and M2

K12: NA62 (Please Add Your Name Here)

M2 Main: NA64mu (L. Molina)

-Installation completed July 14th. Safety clearance 14th in the afternoon.
-Over the weekend we start commissioning and alignment of detectors
-Beam tuning adjusted with Dipanwita at a rate of 5x106 muons/spill
-All our trackers prepared and tested with beam: 11 Micromegas, 4 GEMs and 8 straw detectors.
-Yesterday we calibrate the two VHCAL and the 2 HCAL
-Today we plan to start measuring the hadron contamination in the beam line

H2

H2: NA61/SHINE (Piotr Podlaski)

  • we take stable data
  • yesterday after T2 wobbling change:
    • the beam got signifcantly larger
    • it took us some time to tune it properly - with help of Bastien
    • we had to realign CEDAR
    • K+ content in the beam increased from ~4% to ~5.8%
    • max intensity we can achieve is ~800k/spill - would be nice to have more
    • it would be nice to make the beam smaller - we are in contact with Bastien and Nikos
  • plans for next week:
    • if decrease of the beam size is possible, we will retune DAQ parameters / beam intensity and continue to take data

H4

H4 Outgoing Main: GIF++ (Martin Jaekel, Giuseppe Pezzullo)

  • Very successful beam time, with most setups (12 in total) able to complete their programs.
  • Good beam conditions & very nice sharing of the beam with RD51!
  • Beam pipe installed in the GIF++ bunker for the CMS-ECAL run. Many thanks to all the North area teams and services!

H4 Outgoing Parallel: RD51 (Yorgos Tsipolitis, Eraldo Oliveri)

  • 7/8 team completed the planned measurement.
  • 8th team received detector yestrday -> meaasurement campaign moved to August TB
  • Electron beam: beam quality very good - detector response (timing) good but not as exepected - to be understood / future test in identical conditions expected.
  • Slides with highlights will be uploaded in the indico page by this Friday.
  • Dismounting and RP clearance very smooth (thanks to all the involved teams).
  • Next beam period: 23/08 (2 weeks).

We sincerely express our gratitude to all NA teams (Michael Lazzaroni and team – installation and infrastructure, Francois Grenouilleau and team - handling, David Jaillet and team, gas service - gas, James Devine - safety, Letizia Di Giulio and Jonathan Gulley – flammable gases, Valerie Tromel and team, Frederic Lionel Aberle and team - RP, Alexandre Beynel and team – alignment, Jerome Diego Orand and IT teams and Nikolaos Charitonidis and Bastien Rae – beam).

H4: ECAL CMS (Chiara Amendola)

  • first beams yesterday 19/07 in the afternoon (~16:00), tuning of e±
  • beam energies 20-300 GeV (thanks Bastien Rae)
  • after beam downtime, data-taking resumed in the evening and continued over night
  • trigger delays adjusted for data-taking with ECAL, auxiliary detectors (MCP for timing, hodoscope for beam position monitoring) to be tuned today

ECAL pulses in a readout unit hit by 100 GeV electrons:

  • all going according to schedule
    • ongoing: moving ECAL support positions being mapped to crystals

ECAL crystal matrix, beam over readout unit 42:

  • safety inspection made yesterday for clearance extension, a few items require action from our side

H6

H6 Main: ATLAS HGTD (Stefano Manzoni)

-We have exploit the first week of testbeam to complete the transition of our DAQ setup from Eudaq1 to Eudaq2. Being main (and only!) user have been really helpful to this (a lot of accesses!).
-We are in line we our test-schedule. We have tested for the first time pre-production sensors and we are going to test four new irradiated sensors in the next days.

H6 Incoming Main: EP PIXEL - Week 30 (Peter Svihra)

  • We are planning to resume our high-intensity beam operation needed for testing small pixel detectors
    • the tests may include improving on amount of taken data following previous beam periods where we performed angular scans on iLGAD Timepix3 and Fastpix samples
    • potentially we might test a new H2M technology demostrator
  • Apart from this we hope to:
    • finish our commissioning of MCP-PMT and CFD readout chain for an improved digital timestamp recording
    • commission a cooling setup of our telescope and detectors with proper monitoring of air flow, pressures and temperatures and compare the performance with and without

H6 Incoming Parallel: ALICE ITS3 - Week 30 (Paolo Martinengo)

Plan to install as scheduled

H8

H8 Outgoing Main: ATLAS TILECAL (Tigran Mkrtchyan & Giulio Usai)

A few slides are attached on the indico agenda. Executive summary is described here:

  • Collected complete data with all beam types
    21.6M hadrons
    3.9M positrons
    3.6M muons
    2.7M positrons + 1.8M muons for MAPMT studies
  • Ranging from low 10GeV energies up to 180 GeV
  • Huge improvement in delivered positrons (Thank you!)
  • Cleaner hadron beams with lower electron contamination
  • Cherenkov response still unclear, we will analyse the data and report back
  • All collected data to be processed in the next weeks for more detailed analysis

We would like to thank everyone at the SPS and the North Area.

H8 Main: MGTD TRD (Julia Velkovska and Yulia Furletova)

Our team of 7 people arrived and when through all trinings necessary to operate the beam teast.

We have our prototype detectors delivered. The ArCO2 and N2 gasses were delevered by CERN, and we have secured XeCO2 in collaboration with colleagues from ATLAS-TRT.

Unfortunately, our shipment of readout electronics was delayed to a point where we will not be able to receive it before the end of the test-beam time. We are renting electonics from the CERN electronics pool and buying/borrowing cables and other equipment to improvise a DAQ system.

The box with the support structure for the prototypes arrived at CERN yesterday. We are in the process of retrieving it. The assembly of the setup will follow today/tomorrow.

We re-scheduled our safety inspection for Friday, July 21st at 4 pm.

We discussed the beam parameters with Maarten Van Dijk. He is working on providing the trigger and Cherenkov detectors for PID.

We thank the CERN team for their help and flexibility with our changing schedule.

H8 Incoming Main: POKER (Andrea Celentano)

Goal of the measurement: characterization of the POKERINO calorimeter (3x3 matrix of PbWO4

crystals with SiPM readout) with electrons, at different energies and intensities.

  • POKERINO detector already at CERN. Shipping of remaining equiment (DAQ system, mechanics) on July 25th. Total weight and volume very limited, will be handled by hands by the team (no crane support requested)
  • Team members will arrive at CERN July 25th. All CERN accounts already setup, all safety courses already taken.
  • Technical meeting with Michael Lazzaroni, Maarten Van Dijk, and Silvia Schuh-Erhard on June 27th to define experiment needs in terms of infrastructure (tables, beamline detectors, cables, patch-panels).
  • ISIEC form already submitted.
  • Installation on Wednsday 26th morning in PPE158 (area upstream Morpurgo magnet)
  • Safety inspection scheduled for Wednesday, July 26th at 12.30

Parasitic Users

Reporting for parasitic users is optional, please add your name below:

H4 Outgoing: STRAW TRACKER R&D (Temur Enik, Katerina Kuznetsova)

  • a large program on the straw prototype performance and readout electronics options

evaluation of the realistic noise prediction and thresholds settings in support of the future ASIC development (Dune) - done at H4

evaluation of the TimeOverThreshold mode capability for TIGER-based straw readout (to be continued at the H8 beam dump)

evaluation of the charge measurement requirements for future PID options (signal charge measurements - currently with VMM3 readout - just started, to be continued at the H8 beam dump and during the next test beams)

evaluation of the tracker prototype performance under overpressure up to +1 bar (done at H4, to be extended to +2 bar in the future)

  • we are very grateful to RD51 for their support and help!
  • moved to the H8 beam dump, will be ready for the safety visit early next week (~Monday)

M2: AMBER (Please Add Your Name Here)

M2: MUonE tracker+ECAL (Please Add Your Name Here)

H6: ATLAS MALTA (Please Add Your Name Here)

H8: SND@LHC Hcal calibration (Marco.Dallavalle@cern.ch)

Iron blocks positioned and detectors (Scintillator bars with SiPM R/O and beam counters) installed. Safety inspection (on July 13) OK. Now in commissioning mode. A second safety inspection is planned after addition of SciFi planes in week 30. Start taking data in weeek 31.

H8: QFib (Please Add Your Name Here)

Missing Desy table at PPE158. We can not start instalting with out the table. Therefore we let ATLAS Tile team perform there source test up until now (13:40)

Instalation of QFib is complated. Saftey Inspection will be Thursday 9:30 morning.
After clearence will be ready for beam.

Saftey Clearence is given, we will do the patrol for PPE158 around 11:00

H6 Incoming: MONOLITH - Week 30 (Please Add Your Name Here)

AOB

Minutes by the respective speakers, edited by E. B. Holzer and M. Schwinzerl

There are minutes attached to this event. Show them.
    • 1
      News from the PS & SPS Physics Coordinator
      Speaker: Eva Barbara Holzer (CERN)
    • 2
      PS machine report

      Members of be-dep-ps-coordinators can upload material.

      Speakers: Alexander Huschauer (CERN), Alexandre Lasheen (CERN), Benoit Salvant (CERN), Bettina Mikulec (CERN), Denis Gerard Cotte (CERN), Matthew Alexander Fraser (CERN), Ruben Garcia Alia (CERN)
    • 3
      SPS machine report
      Speakers: Arthur Spierer (CERN), Carlo Zannini (CERN), Francesco Maria Velotti (CERN), Giulia Papotti (CERN), Kevin Shing Bruce Li (CERN), Michael Schenk (CERN), Stephane Cettour Cave (CERN), Verena Kain (CERN)
    • 4
      Safety / Radiation Protection
      Speakers: Alex Schouten, Evelyne Dho (CERN), James Devine (CERN), Jean-Francois Gruber (CERN), Laura Jayne Rowland (CERN), Letizia Di Giulio (CERN)
    • 5
      nTOF
      Speakers: Alberto Mengoni (ENEA & INFN, Bologna), Michael Bacak (CERN), Nikolaos Patronis (University of Ioannina (GR))
    • 6
      East Area Beam Status
      Speakers: Bastien Rae (CERN), Dipanwita Banerjee (CERN), Johannes Bernhard (CERN), Maarten Van Dijk (CERN), Michael Lazzaroni (CERN), Nikolaos Charitonidis (CERN)
    • 7
      East Area Users Tour de Table
      • a) T8: IRRAD / CHARM
        Speakers: Federico Ravotti (CERN), Giuseppe Pezzullo (CERN), Salvatore Danzeca (CERN), Salvatore Fiore (CERN)
      • b) T9 Main: WCTE

        Members of ps-sps-users e-group can upload material

      • c) T10 Outgoing Main: ALICE ITS3

        Members of ps-sps-users e-group can upload material

      • d) T10 Outgoing Parallel: ALICE TIMING

        Members of ps-sps-users e-group can upload material

      • e) T10: BL4S

        Members of ps-sps-users e-group can upload material

      • f) T10 Incoming: RE21 CBM (Week 30)

        Members of the ps-sps-users e-group can upload material

    • 8
      Outgoing: HiRadMat

      Members of ps-sps-users e-group can upload material

    • 9
      North Area Beam Status
      Speakers: Anna Baratto Roldan (CERN), Bastien Rae (CERN), Dipanwita Banerjee (CERN), Johannes Bernhard (CERN), Michael Lazzaroni (CERN), Nikolaos Charitonidis (CERN)
      • a) Status of H2, H4, H6, and H8 Beamlines
      • b) Status of P42 and K12 Beamline
      • c) Status of M2 Beamline
    • 10
      North Area Users Tour de Table
      • a) K12: NA62

        Members of ps-sps-users e-group can upload material

      • b) M2 Main: NA64mu

        Members of ps-sps-users e-group can upload material

      • c) H2: NA61/SHINE

        Members of ps-sps-users e-group can upload material

      • d) H4 Outgoing: GIF++ (Main), RD51 (Parallel)

        Members of ps-sps-users e-group can upload material

      • e) H4: CMS ECAL

        Members of the ps-sps-users e-group can upload material

      • f) H6 Main: ATLAS HGTD

        Members of ps-sps-users e-group can upload material

      • g) H6 Incoming: EP PIXEL (Main, Week 30), ALICE ITS3 (Parallel, Week 30)

        Members of ps-sps-users e-group can upload material

      • h) H8 Outgoing Main: ATLAS TILECAL

        Members of ps-sps-users e-group can upload material

      • i) H8 Main: MGTD TRD

        Members of ps-sps-users e-group can upload material

      • j) H8 Incoming Main: POKER

        Members of ps-sps-users e-group can upload material

      • k) Parasitic Users

        Reporting is not obligatory,
        Members of ps-sps-users e-group can upload material

        • H4 Outgoing: STRAW TRACKER RD
          Also: Incoming as parasitic user in H8 behind DUMP

        • M2: AMBER

        • M2: - MUonE tracker+ECAL
        • H6: ATLAS MALTA
        • H8: SND@LHC
        • H8: Qfib

        • H6 Incoming: MONOLITH (Week 30)

    • 11
      AOB