Description
This presentation outlines the ongoing developments in the RF straight sections located around points H and L, with a particular focus on the new designs of the 400 MHz and 800 MHz cryomodules, including the rationale for their specified dimensions. Integration studies are being carried out with careful consideration of spatial constraints, all within the 5.5 meters internal diameter of the tunnel. These constraints include underground infrastructure elements (such as access shafts and connection tunnels), the available straight section length, the dimensions of the cryomodules, and the provision of general services, such as electrical supply, cooling, and ventilation. Transport clearance volumes are also considered. The presentation will highlight current challenges encountered in the integration process as identified during the feasibility study and will explore potential solutions currently being considered for the pre-TDR phase.