Gas systems weekly project meeting

Europe/Zurich
32/1-A24 (CERN)

32/1-A24

CERN

40
Show room on map
gas systems project meeting
Zoom Meeting ID
62095888225
Host
Beatrice Mandelli
Useful links
Join via phone
Zoom URL

piquet:

3/4

CMS-RPC purif 1 not doing vacuum during regeneration (TICKET)

ALICE-TRD Xe recuperation how to inject (TICKET)

27/3

MDT humidifier -> Checklist back for all!

20/3

CMS-RPC purifier 1 not reaching the pressure for phase 2 --> to check why (TICKET)

CMS change cap closed-open and ventilation --> for Salvatore e Aleksandar -> it was a mistake from the operator

 

dove sono i ticket di cavern closure dei quattro?

 

checklist dove sono? --> ticket IO [GASSYSTEMS-573] weekly checklists files missing: ATLAS and CMS - CERN Central Jira

 

TOO MANY ENTRY FOR DATAPOINTS -> TICKETS

 

ALICE

70 report from Anité [GASSYSTEMS-70] TPC gas quality - filters to Benoit - CERN Central Jira (I don't see the report, can you please add it?)

HMPID start on April 1st. 

 

 

ATLAS

MDT high flow (wrong mixture, CO2 injected instead of Argon): how to spot in advance?

MDT pump: supplier reply? frequency converter? --> Philipp to be informed that some test at some point will be needed (TICKET)

TGC fill on April 1st. Still confirmed after the He leak problem? --> ticket? IO --> April 8th

check nC5H12 stock -->ticket IO [GASSYSTEMS-574] ATLAS-TGC nC5H12 stock - CERN Central Jira

ticket for RPC purifier not working & alarm blocked --> IO

termination DP-PA for RPC --> ready? for next week w13-> ticket w14 -> IO [GASSYSTEMS-575] ATLAS-RPC profibus warning at pump module - CERN Central Jira

heating controllers for ATLAS --> ticket IO -> out od yets & Patrick for cost estimate [GASSYSTEMS-576] ATLAS heating pipe cabinets - CERN Central Jira

 

 

CMS

CF4 pressure sensors for vacuum received --> test needed -> w14 [GASSYSTEMS-577] CF4 absorber new vacuum pressure sensors - CERN Central Jira

R134a insulation - isol'tut to check and see what to do -> ticket IO [GASSYSTEMS-578] R134a insulation - isol'tut to check and see what to do - CERN Central Jira

How much gas flow we need for the RPC purifier? --> OFFLINE with Maria Cristina [GASSYSTEMS-579] CMS-RPC How much gas flow we need for the RPC purifiers? - CERN Central Jira

RPC double flow test -> ticket? exists? [GASSYSTEMS-392] RPC test of double the flow in one rack - CERN Central Jira

GEM chamber pressure alarm for stop -> ticket with GEM responsible [GASSYSTEMS-580] GEM chamber pressure alarm for stop - CERN Central Jira

GEM 904 would like to move their mixer to PLC -> ticket already exists. check  [GASSYSTEMS-468] Re: 904 GEM gas system - CERN Central Jira

CSC 904 new panels -> for LS3 -> ticket Andrea? [GASSYSTEMS-581] CSC at 904 - CERN Central Jira

RPC 904 new line -> ticket Andrea? [GASSYSTEMS-582] RPC 904 new line - CERN Central Jira

RPC904 cleaning of lines -> follow ticket [GASSYSTEMS-556] 904 RPC gas distribution panels not working properly - CERN Central Jira

R134a Upgrade (hardware and software) to be tested -> TICKET

 

LHCb

SciFi and UT vaisala calibration check -> done -> there was a ticket?

[GASSYSTEMS-563] SciFi vaisala check - CERN Central Jira DONE

[GASSYSTEMS-564] UT vaisala check - CERN Central Jira DONE

SciFi software modification to be installed --> Patrick to check

CODEX-b --> purif to be prepared, calibration of O2 and some test  -> ticket? IO [GASSYSTEMS-466] CODEX commissioning - CERN Central Jira

RICH1 mixer modification --> 1 card to add --> Patrick > there was a ticket?

LHCb console in US not working -> to Gianluca [GASSYSTEMS-583] LHCb console in US not working - CERN Central Jira DONE

should we postpone real filling? Patrick to ask Christoph [GASSYSTEMS-584] RICH1: should we postpone real filling? - CERN Central Jira UPDATE

RICH2 CO2 from purifier-> check how to decrease-> ticket IO [GASSYSTEMS-585] RICH2 [CO2] from purifier-> check how to decrease - CERN Central Jira

 

NA62

email to David for anticipate the date of filling --> Roberto

CEDAR filling planned for April 14th -> CHECK TICKET

pressure sensors S/N to follow -> check TICKET

 

non-LHC safety valve --> check lista di Fabio

[GASSYSTEMS-172] non-LHC safety valves to be verified - CERN Central Jira

ELOG - safety valves to be verified for non-LHC systems

Fabio for R134a line to MolSieve R&D

 

 

Additional requests/projects/discussions

New Gas panels for DRD1 test beam [GASSYSTEMS-586] RE: New Gas panels for DRD1 test beam - CERN Central Jira

887 CEDAR new "mixers" --> TICKET

 

 

examples of topics for the common discussions:

 

-cms id flushing -> Andrea

-cms r134a operation and spare -> Andrea

-cms cf4 operation and spare -> Andrea

-atl tgc nc5h12 -> Kacper

-Analysis boxes -> LPh

-C4F10 new recuperation installation -> Patrick

 

There are minutes attached to this event. Show them.
    • 09:00 09:05
      New arrival: Miguel Gonçalo Alves Ramos da Silva Afonso 5m
      Speaker: Miguel Afonso (Universidade de Lisboa (PT))
    • 09:05 09:15
      Piquet interventions 10m
      Speakers: Gianluca Rigoletti (CERN), persons on piquet
    • 09:15 09:45
      YETS tickets/planning 30m
      Speakers: Andrea D'Auria (CERN), Beatrice Mandelli (CERN), Gianluca Rigoletti (CERN), Kacper Kapusniak (CERN), Louis-Philippe De Menezes (CERN), Patrick Carrie (CERN), Roberto Guida (CERN)
    • 09:45 10:15
      Review new ticket or updated during current week 30m

      Jira dashboard: https://its.cern.ch/jira/secure/RapidBoard.jspa?rapidView=9098&view=detail
      Confluence page: https://confluence.cern.ch/display/KBFGS

      Speaker: Roberto Guida (CERN)
    • 10:15 10:25
      gas systems status during yets 10m
    • 10:25 10:30
      other M&O news 5m
      Speakers: Beatrice Mandelli (CERN), Gianluca Rigoletti (CERN)
    • 10:30 10:35
      Gas mixture analysis for LHC experiments 5m

      https://epdt-gasmonitoring.web.cern.ch/

      Speaker: Maria Cristina Arena (CERN)
    • 10:35 10:40
      FSU planning for coming weeks & Jobs status 5m
      Speaker: Andrea D'Auria (CERN)
    • 10:40 10:50
      Pump working hours, EAM/Infor, maintenance and spare parts follow-up 10m
      Speaker: Miguel Afonso (Universidade de Lisboa (PT))

      any maintenance performed from last Thursday?

      ALICE

      27/3 MID 4201 

       

      ATLAS

      3/4 RPC purif 1 pump

       

      CMS

      27/3 DT 4101 + 4201

      3/4 RPC purif 1(tbc) pump

    • 10:50 11:00
      list of projects for 2025 and beyond 10m
      Speaker: Roberto Guida (CERN)
    • 11:00 11:10
      procedures summary 10m
      Speaker: Roberto Guida (CERN)
    • 11:10 11:20
      aob 10m
      Speakers: Amin Bouzaiene (Politecnico di Torino (IT)), Andrea D'Auria (CERN), Beatrice Mandelli (CERN), Burkhard Schmidt (CERN), Damiano Galassi, Gianluca Rigoletti (CERN), Kacper Kapusniak (CERN), Louis-Philippe De Menezes (CERN), Maria Cristina Arena (CERN), Mattia Busato (CERN), Mattia Verzeroli (Universite Claude Bernard Lyon I (FR)), Michal Zbigniew Zimny (CERN), Paolo Petagna (CERN), Patrick Carrie (CERN), Pieter Vanslambrouck, Roberto Guida (CERN), Stefania Juks (Université Paris-Saclay (FR))

       

      DAMIANO:

      • R134a Distillation I only see Fabio available but also Abdel is needed for welding volumes/buffers/column (at least one full week). If we do not proritize this part me and Fabio will have to stop at a certain point. So it would be better to have them in parrallel or Abdel first.

       

      CMS-RPC-904

       

      CHARM test

      • pressure sensor test