AFP plans for interventions during TS1:
AFP was planning to install PicoTDC based ToF system, as an upgrade to the current low rate capability HPTDC, however encountered unforeseen hardware and dedicated/crucial manpower issues after production and therefore will postpone this intervention to YETS 2025/26.
Other TS1 plans are related to software and calibration work which does not necessitate access to LSS1.