Lab b1:
- (the first) safety inspection took place
- all HV connections on the prototype need to be covered
- RP needs to validate the lab and source storage
- AC installation to be finished by the end of June
Intermediate prototype:
- improved shielding installed
- double-sided readout with fast ROBs tested with two straws
- signal attenuation to be evaluated
- new gas bottle ordered and
Long prototype:
- HV plug and HV cap prototype parts received, QC ongoing
- parts to be ordered as soon as possible
- spacer fixation to be finalized
- parts to be ordered as soon as possible
- HV board modified (added 2 holes), to be cleaned
- straw fixation plates were cleaned
- discussion about gasses to test and order
FCC:
- introductory presentation given by Hans at Allegro meeting
- need to understand the requirements from FCC
There are minutes attached to this event.