Task force - RA building optimisation #19

→ Europe/Zurich
30/7-010 (CERN)

30/7-010

CERN

20
Show room on map
    • 14:30 → 14:35
      Approval of previous minutes and review of actions 5m

      Summary of Actions :
      .

      1. BA80 worksite: Cat 1 - Sign the responsibility page and send it to Olivier Prud’Homme – Cédric Halbert. ==> CLOSED
      2. Q1 - Contact Hervé Prin to ask for a written confirmation about the storage of Q1 under two levels – Cédric Halbert. ==> CLOSED
      3. B887: Contact Maxime Dumas to request a second spreader bar until mid-October – Sarah Moralent. ==> CLOSED
      4. B954: Contact Laurent Croses to check if he has an additional block turning device. – Sarah Moralent. ==> Cancelled
      5. B954 Bunker: Invite Damien Grenier to inspect items inside the bunker and decide on disposition – Cédric Halbert. ==> on going
      6. B887: Launch the procurement process for the wooden blocks – Cédric Halbert/Sarah Moralent. ==> CLOSED
      7. Late request ID481 - Clarify the situation regarding the proposed storage of the power converters in front of B961 and identify possible alternatives before any storage solution is validated - Sarah Moralent ==> CLOSED (40 m2 in front of B684 are enough)
      Speaker: Dr Germana Riddone (CERN)
    • 14:35 → 14:40
      General news 5m
      Speaker: Dr Germana Riddone (CERN)
    • 14:40 → 14:50
      Update of the requests and update of layouts 10m
      Speaker: Cedric Halbert
    • 14:50 → 15:10
      Installation of the B954 bunker 20m
      Speaker: Sarah Moralent
      Etat d'avancement et planification bunker B954
    • 15:10 → 15:15
      Dashboard of 879/954/955 5m
      Speaker: Alexandre Foraz
    • 15:15 → 15:25
      Tranfert of assets to liberate space in B954/955 10m
      Speakers: Elsa Clerc (CERN), Sarah Moralent
    • 15:25 → 15:35
      Status of the support structures 10m
      Speaker: Julien Prosic