ISOLDE Technical Coordination Meeting (LS3)
-
-
14:00
→
14:05
General news - Review of minutes 5mSpeakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN)
-
14:05
→
14:15
Safety matters 10m
https://home.cern/tag/ls3-safety-spotlight/
Speakers: Andreas Herty (CERN), Hanne Heylen (CERN), James Devine (CERN), Joachim Vollaire (CERN) -
14:15
→
14:20
IBDRS project update - Work in the primary areas - BTY line @ 2 GeV 5m
FCEN adaptation for work in Build. 197 scheduled tomorrow (12/11). New power supplies arrangement between 197 and 361
Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN)FCEN adaptation for work in Build. 197 scheduled tomorrow (12/11). New power supplies arrangement between 197 and 361
Preparatory work for the Frontends.
GPS Frontend (valve leak between GPS10 and GPS20). Discusison with TE-MSC, leak is small and not penalizing for operaiton. Situation to be reassessed but the baseline is not to perform the change. Still the LS can be used to "prepare" a possible intervention.
-
14:20
→
14:25
RILIS Laboratory upgrade project - Exhaust gas line re-routing - activities update 5mSpeakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
- Fire extinguisher position outside HRS door (see attached file)
- Shielding on back wall of RILIS installed yesterday
- 2 blocks undelivered - arriving mon 16th, will be installed with the tables
- Everything went relatively smooth! Thanks to all who helped
- Shoring to be dismantled tomorrow
- Boris tube
- Installation of support beams wed 18th next week
- Boris tube core drilling Fri 20th
-
14:25
→
14:30
Machine related activities in the experimental hall 5mSpeakers: Erwin Siesling (CERN), Simon Mataguez (CERN)
FEs :
- The HRS10 sector elements cables were connected back on the patchpanel in the HRS sep zone (thanks Stefano). Powering tests were carried out (Miguel). YHRS.QP30-R seems to hold up to 3.5kV correctly. QP30-L, as expected, shows a 'short'. Further investigation on the FE side is necessary.
- Tests GPS10/20 sector valve (leaking) done: reporting Miguel
Platform EPC / HW tests:
- During automatic testing two devices went into fault (FGSC93/VS_FAULT): YCB0.KI0700A and YCB0.KI0700B. After combined effort in investigation (Nicolas, Lefteris, Miguel, Emiliano) the issue has been pinned down. These bipolar power supplies don't like to pass through 0V. Swicthing them off at 0V is a solution but when using auto tuning tols and going through 0V this fault could be an issue.
-
First FE correctors YHRS.DH0100-V, YHRS.DV0100-V, YHRS.DH0200-V, and YHRS.DV0200-V now have two bipolar power supplies instead of 4 single ones. The virtual devices will need adaptation accordingly (Lefteris?). Same goes for the GPS side. to follow-p (Miguel).
- This is the last week when tests can be carried out: Mon 16th Nov vacuum exhaust lines flushing, etc. - vacuum stop. Vacuum system fully consigned Mon 23rd. Rerouting of the (RILIS related) vacuum exhaust tubes - no VSC til May '27.
REX/HIE ISOLDE:Ongoing:
- REX RF room (G. Piccinini):
Scaffolding for yellow passerele reinforcement calculations ongoing - installation forseeen in Dec. Removal old equipment Jan-Feb.
Modifications CV systems for the new solid state amps Feb-May
New amps installation after CV modifications (as of May '27)
Scaffolding not to stay any longer than necessasry for removal: The opening is needed for any REX Low E or other equipment in that zone. Calculations to be done for the installation of the new equipment (sizes). - REX digital LLRF status meeting held 10 Nov: GRAD/QUESt being hired, starts Feb '27. Conceptual design D. Valuch, Implementation GRAD, uTCA support within RF group, Budget ok from consolidation. Aim for REX RF system (solid state amplifiers & digital LLRF) commissioning March '28.
- REX Low E development:
Mass slits acctuator replacement: Dedicated meeting Fri 6 Nov (M. Nieto, A. Rodriguez, E. Siesling)
Replacement for one of the HIE slits actuators. Adapted nipple to a new flange. Additional FC, 3 different postiions and slit opening sizes. Existing FC stays - interlock for in positions. Concept being worked out (M. Nieto)
Budget: BI group - REXTRAP innner structure work ongoing in 179. (J. Schoonwater, F. Wenander).
- HIE ISOLDE related BI work:
BI consolidation budget available - new strategy instrumentation upgrade: (dedicated meeting held S. Maraguez, M. Nieto)
- installation 7 newest actuators + 1 spare (instead of only 3 and strategic reshufflling)
- replacement of 3 slit plates by vertical square collimator slits
- recalibration 10 diagnostic boxes
Separator zones HRS & GPS/HRS entrance area:
- Field regulation old measurement cables removed form the HRS zone - next to RP buffer zone, to be checked (ask RP)
Measures taken for future DCCT box placement and field regulation equipment boxes at the magnets 90 & 60
Cable requests gone out for the new system. PLAN (14522) created for the field regulation installation works (M. Torre / E. Siesling). ECR to be done? - Old Tapestation rack to be moved to the SAS for transport (Ricardo will recuperate it) -> handling request to be made (ES): rack to be moved through opening next to REX.
- Installation new cable trays under RILIS as of next week - assume as of wk48/ 23 NOV with PUMA AC work in wk47 in mind? Is it useful to have the new field regulation rack in place before this starts?
Infrastructure / 197 BTY / Separators Power supplies consolidation:
- 197 installation CV tubing works ongoing: See comments J. Vollaire
- Chilled water / AC in 508 and for the 170 HVAC system situation update?
- Return cooling water / restart '28: EN/CV study on a possible different routing of the cooling water piping so that it is diconnected from the IBDRS civil works. Possibility via the roof of 170 discarded by SCE. Dedicated meeting on future pipes rack re-installation window 20 Nov. (A. P. Bernardes, CV, S. Deleval, N. Szczepanik-Scislo, G. Petrika, A. Fournier EN/CV)
Fume cupboards GLM/GHM:
- New chemical fumecupboard in old ICR: - Possibilities being investigated in parallel with 197 works (N. Szczepanik-Scislo, A. Fournier, V. Barozier)
Fiber Optics work / ISOLDE timing upgrade:
- ISOLDE Central Timing Renovation - Functional and operational requirments being written by J. Sanchez
Regular meetings (L. Nies, E. Piselli, G.P. Di Giovanni, Controls groups). This includes the CAO switching, REX timing upgarde, MR-Tof/PUMA, beamgate cons. - New beamgates power supplies to be installed in the OICR rack 03: Agreed is to move the 3 FEC's - equipment owners been contacted (L. Nies). Status?
GHM line:
- a new end vacuum valve has been installed to replace the compressed air leaking old one, however, the new valve has a configuration of a tube for its vacuum gauge which stands out on the front top which is an issue for the setup: Guilherme is in contact with the vacuum team (Jose, Guillermo) and several solutions have been proposed - to follow up.
Other:
- A survey poteau (POT3) was kick off the wall ('Einstein' wall of 170) when transport passed with one of the small cranes needed ror the shielding blocks handling at RILIS. Survey team has been informed (A. Behrens, A. Beynel BE/GM) - not too much of a problem. It will be reinstalled at the next survey geo system measurements for the hall (on the list of Alexandre Beynel).
- 14:30 → 14:35
-
14:35
→
14:40
Experiments related activities in the experimental hall 5mSpeaker: Erwin Siesling (CERN)
ISOLTRAP:
- Re-installation of infrastructure and equipment ongoing (A. Jaries)
- AC cabling to be discussed with EN/EL P. Gallay and new contractor (L. Nies, A. Jaries, E. Siesling)
- Next week: Crane lock-out wk47: dewar handling planned for Fri 20 Nov - OK (see PUMA AC cablling works below)
COLLAPS/CRIS platform:
- Users COLLAPS and CRIS have removed mainly all of their equipment including mirror boxes and some of the supports and laser tubes (those reachable) and is ongoing. Ready for installation of the scaffolding as foreseen next week (wk47: 18/19 Nov)
- Planning: Tranport and SCE (G. Venel & team, M. Boubon, S. Grail (Ouvaroff), S. D'Armancourt) for the removal of the concrete structure:
First stage:
- wk 45/46: removal as much as possible of the equipment / mirror boxes, etc. - Users in situ 2 wks (2-13 Nov) (Liss, Kara, Jessica, Tim) - done
- wk 47 (probably 18/19 Nov): scaffolding for transport to prepare for the handling of the large beam (8m, 6 ton) + access to remove supports, laser guidance tubes, etc. (Ask O. Fjeld + users? + E. Siesling)
- wk 47/48 (as of 23 Nov): the large concrete beam will be removed + 2 small 80x80cm blocks (transport, G. Venel)
- wk 48 cutting up of the concrete beam in 3 pieces in the ISOLDE hall (PUMA area, wet cutting with plastic SAS) (SCE, S. D'Armancourt) - dates cutting to be confirmed - BC needed for the cutting work / offer received (S. D'Armancourt)
For this the area behind Miniball / PUMA needs clearing/moving of some items - action E. Siesling, H. Heylen, users
second stage:
- removal of the scaffodling WK48/49
- followed by removal of the services on the tall concrete blocks (RP monitors, cable trays, AC distribution). AC distribution removal (keep boxes) discussed with P. Gallay EN/EL - ticket probably enough
- removal of the tall concrete blocks
-timeline: before the end of the year - Organisational structure being put in place (H. Heylen et all.)
PUMA:
- As of next week:
- AC cable installation will start next week wk47 (16-20 Nov) from 199 along the walls in the HIE side of the hall to a new LC7 AC cabinet.
- Crane will be locked out wk47 / in parallel with scaffodling work at CRIS/COLLAPS: - ISOLTRAP dewar Fri 20th morning should work, Ok with REX team.
- extra I-pillar for the AC cabinet and small I-beam + hor beam for AC boxes will be placed by the contractor: Attn. Please keep an eye on position: L. Nies, M. Kirschbaum
- AC cable holders side of LC7 later (2 AC power cables: PUMA footprint length + 2 meters) - AUG control cable needs to be pulled from the PUMA AC cabinet (LR7): wk47/48 -> to be coordinated with COLLARIS scaffolding installation and 197 CV works (EN/EL, E. Siesling, A. Fournier, J. Vollaire)
ISS
- Still in place: Transport would like to borrow the yellow ISS end shielding plates carrier for a few days for a handling actiovity at CNGS - ISS owners OK (A. Dolan, L. Gaffney)
-
14:40
→
14:45
Status of ECRs 5mSpeaker: Simon Mataguez (CERN)
-
14:45
→
14:55
Mechanical Workshop and other support requests 10mSpeaker: Oscar Fjeld (CERN)
Work in progress:
- COLLAPS (187) - milled the replacement bronze slide; nearly complete

Development and follow-up:
- ASCII sample holder solution (178) - reviewed the sample-holder drawings and STEP models; prepared a C1 concept, to be revised.

- Miniball Preamplifier structure (190) - concept discussed with Carlotta and design is ongoing.
New requests:
- Miniball - IC gas-system adapters: request for stainless-steel adapters between NPT and M12x1 Festo connections; final sizes to be confirmed.
- REX-EBIS - Aluminium component manufacturing (ST2670408 and ST2677367)
- RC6 - Cutting of metal panels: new request to cut marked panels to fit the HV cage.
-
14:55
→
15:00
Planned visits and AOBs 5mSpeaker: Hanne Heylen (CERN)
- Visits
- Friday 13/11 13:30 - 24p
- Saturday 21/11 10:30 - 24p
- Work technical gallery 833 - access road 508
- 2 parking places blocked until end of the year
-
Anyone need any guardrails? See photo attached. If so please get in touch with Severin, otherwise they will go to waste.
Le montage de la grue est prévu pour mardi et mercredi 17-18/11/2026.
Veuillez trouver en PJ les informations mises à jour par rapport à la réunion du 16/10, ainsi qu'une affiche à transmettre aux utilisateurs pour information.
Un balisage sera mis en place dès le 16/11pour la fermeture du parking.
La journée du 18/11 l'entreprise mettra en place le balisage et des hommes trafics pour la circulation.
Le levage de la flèche, qui nécessite l'évacuation des bâtiments avoisinants, prendra 15-20 minutes et je vous confirmerai lorsque l'opération est terminée.
- Visits
-
14:00
→
14:05