FEs :
- Tests were carried out by Lukas Nies on the HRS.QS30-L on the FE side. Good news: The issue of short was found in the cable from the FE to the HRS Sep zone, not on the machine side/inside the Quad. - reporting Lukas
Platform EPC / HW tests:
- The issues with devices going into fault when going through 0V using automatic testing seems to be understood. However, Miguel is experiencing simular issues at MEDICIS - reporting Miguel.
- The vacuum system was stopped on Monday 16 Nov in view of the flushing and preparation of the exhaust lines rerouting - no VSC til May '27.
- Rerouting of the vacuum exhaust lines: See RILIS reporting.
REX/HIE ISOLDE:
- Visit on Mon 16 Nov of D. Valuch and the SY-RF-CS team to the REX LINAC and REX RF room to identify and define the hardware, timeline and resources for the PLC needs. Copy of the LINAC3 system but still the timeline (2027) is tight with their other activities in mind.
- Budget ok from consolidation. Aim still for REX RF system (solid state amplifiers & digital LLRF) commissioning March '28.
- REX Low E development:
New Mass-slits system at the REX Separator concept being worked on (M. Nieto) - news?
- REXTRAP innner structure work ongoing in 179. (J. Schoonwater, F. Wenander).
- HIE ISOLDE related BI work:
New strategy instrumentation upgrade:
- installation 7 newest actuators + 1 spare (instead of only 3 and strategic reshufflling)
- replacement of 3 slit plates by vertical square collimator slits
- recalibration 10 diagnostic boxes
Follow-up meeting Tues 17 Nov (S. Mataguez, M. Nieto, et all.)
HIE Cryo systems:
- Visit in 199 with the cryo team (L. Stewart, T, Dupont TE-CRG) for the implementation of a bypass valve box, evaporator and recuperation line (to the service gallery and Meyrin Cryo plant) in view of the full integration of the 2kL LHe dewar
- Integration concept done by Cryo: V. Barozier will be contacted to integrate in the overall model and check for clashes: Attn. Check with the as built situation
- Installation will be done in the cause of 2027 with the aim to have all ready for commissioning together with the cryo plant end '27/start up '28
Separator zones HRS & GPS/HRS entrance area:
- Field regulation old measurement cables removed form the HRS zone - have been checked by RP, MSC will recuperated the rolled up ones for their lab.
Cable requests gone out for the new system. PLAN (14522) created for the field regulation installation works (M. Torre / E. Siesling).
- Old Tapestation rack will be moved to the SAS for transport (Ricardo will recuperate it) -> handling as of Fri 20 Nov.
- Installation new cable trays under RILIS as of week 48? News?
Infrastructure / 197 BTY / Separators Power supplies consolidation:
- 197 installation works ongoing: See comments J. Vollaire
- Chilled water / AC in 508 and for the 170 HVAC system situation update?
- Dedicated meeting on future pipes rack re-installation window 20 Nov. (A. P. Bernardes, CV, S. Deleval, N. Szczepanik-Scislo, G. Petrika, A. Fournier EN/CV) -> Water to be back in summer '27 and moreover in Jan '28 for the facility restart.
Fume cupboards GLM/GHM:
- New chemical fumecupboard in old ICR: - possible to route the duct through the ceiling along the wall. Small modification identified: earth connections and cable tray as well as displacement of items on the 197 wall - action Joachim/Erwin + integration Vincent: during 197 EN/EL works (N. Szczepanik-Scislo, A. Fournier, V. Barozier)
Fiber Optics work / ISOLDE timing upgrade:
- ISOLDE Central Timing Renovation - Functional and operational requirments being written by J. Sanchez
Regular meetings (L. Nies, E. Piselli, G.P. Di Giovanni, Controls groups). This includes the CAO switching, REX timing upgarde, MR-Tof/PUMA, beamgate cons.
- Digital LLRF for REX would also need White Rabbit timing (first LLRF to use..) - Ioan Kozsar, Evangelia Gousiou BE-CEM, Grzegorz Kruk BE-CSS been made aware (G.P. Di Giovanni)
GHM line:
- The end valve has been turned so that there is no conflict with future experiment installation (J. Somoza)